Bangalore/Project record

K-RERA · the public record

SUMADHURA NANDANAM

Bengaluru East · SUMADHURA INFRACON

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Dec 2021declared completionK-RERA registration · read 25 Oct 2026
250registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

2.6registered acres

96.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for SUMADHURA NANDANAM

K-RERA · PRM/KA/RERA/1251/446/PR/180507/001667

Project facts and comparisons

On the register

Declared completion31 December 2021
Land area10,488 sq m (2.6 acres)
Homes registered250
Tower/wing entries3

In context

Density96.5 homes per acre
Density in context82nd percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units250Total inventory registered with K-RERA.
Registered land area10,488 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.98Sanctioned floor-area ratio (≈31,276 sqm sanctioned FAR area ÷ 10,488 sqm land) — higher means a denser vertical build.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)250Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date26-03-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BLOCK A147272-
BLOCK B148888-
BLOCK C149090-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 250 official flat/unit rows, matching the 250 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK16655.9-76.9 sqm26.6-37.2 sqm166
2.5 BHK4395.6-96.9 sqm45.0-46.1 sqm43
3 BHK41101.1-112.4 sqm49.9-54.9 sqm41

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLOCK C9071.3-112.4 sqm33.6-54.9 sqm90
BLOCK B8855.9-96.9 sqm26.6-46.1 sqm88
BLOCK A7274.2-101.1 sqm36.2-53.0 sqm72
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A301BLOCK A33 BHK101.1 sqm53.0 sqm1
A302BLOCK A32 BHK76.9 sqm37.2 sqm1
A303BLOCK A32 BHK76.9 sqm37.2 sqm1
A304BLOCK A32 BHK74.2 sqm36.2 sqm1
A305BLOCK A32 BHK74.2 sqm36.2 sqm1
A306BLOCK A32 BHK74.2 sqm36.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 26 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2021, extended (Covid Extension) to 30 Sep 2022 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: BESCOM
Water & sewage (BWSSB/KWSSB)Document listed: BWSSB
Fire NOCDocument listed: Fire Force Department
Pollution control (KSPCB)Document listed: KSPCB
Environmental clearanceDocument listed: SEIAA
Airport Authority height clearanceDocument listed: Airport Authority of India

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/220121/0008846
21-01-2022
BUILDER DEMANDING AN ADDITIONAL Rs 3.27 lakhs TO COMPLETE REGISTRATION OF FLAT B 203SUMADHURA NANDANAMDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectA.Dellibabu-2010Chowdeswari Layout, Marathahalli
Structural engineerB E Pruthviraj---

Builder track record

RERA filing

Sumadhura has 28 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sumadhura Infracon”) (average reported construction progress 54%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹44.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: HDFC RICHMOND ROAD (IFSC HDFC0000523, a/c …1431). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt7 km
Outer Ring Road / Manyata12 km
MG Road / city centre12 km
Electronic City17 km
Kempegowda Int'l Airport23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sumadhura Infracon. View Sumadhura Infracon's full track record →
Sumadhura Infracon has 21 projects registered in Bangalore.

Other projects by this builder in Bangalore

Folium BY Sumadhura Phase-III
Filing overdue · 89% built · 72% sold
Folium BY Sumadhura Phase-IV
Filing overdue · 38% built · 12% sold
Hive BY Sumadhura
Filing overdue · 54% built · 7% sold
Sarang BY Sumadhura Phase-I
Filing overdue · 91% built · 67% sold
Sarang BY Sumadhura Phase-II
Filing overdue · 60% built · 61% sold
Sumadhura Capitol Residences
Filing overdue · 59% built · 58% sold

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.