Bangalore/Project record

K-RERA · the public record

UNIQUE FERONIA

Hosakote · Unique Construction

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Dec 2021declared completionK-RERA registration · read 21 Sep 2026
63registered unitsK-RERA registration · read 21 Sep 2026

The record · free to read

Registration read 21 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 21 Sep 2026

Inventory & scale

What this registration contains.

Row houses
63

Filed categories, unchanged · K-RERA registration · read 21 Sep 2026

The whole registration

1.9registered acres

32.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/190107/002280

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion15 December 2021
Land area7,840 sq m (1.9 acres)
Homes registered63
Tower/wing entries6
Unit mix63 × Row houses

In context

Density32.5 homes per acre
Density in context18th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units63Total inventory registered with K-RERA.
Registered land area7,840 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)63Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field70Separate filed counts; these categories may overlap and are not added together.
Project start date07-11-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Row houses63100%0 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
ILANA11515-
SIERRA31212-
MEADOW31212-
TERRA31212-
RAINE188-
FLEUR144-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 63 official flat/unit rows, matching the 63 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK DUPLEX6381.2-122.4 sqm89.9-156.5 sqm63

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
ILANA1596.7-101.2 sqm115.1-126.1 sqm15
MEADOW1284.0-121.3 sqm93.2-156.5 sqm12
SIERRA1284.0-121.3 sqm93.2-156.5 sqm12
TERRA1281.2-117.7 sqm89.9-154.1 sqm12
RAINE881.2-113.7 sqm89.9-126.8 sqm8
FLEUR4109.6-122.4 sqm123.1-130.8 sqm4
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
I-01ILANA03BHK DUPLEX101.2 sqm122.5 sqm1
I-02ILANA03BHK DUPLEX100.7 sqm115.1 sqm1
I-03ILANA03BHK DUPLEX100.7 sqm115.1 sqm1
I-04ILANA03BHK DUPLEX100.7 sqm115.1 sqm1
I-05ILANA03BHK DUPLEX100.7 sqm115.1 sqm1
I-06ILANA03BHK DUPLEX100.7 sqm115.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 22 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 15 Dec 2021, extended (Section 6 Extension) to 30 May 2023 — both dates have passed with no OC on file. The extension on file was granted on 29 Mar 2023 (K-RERA extension no. EX/PRM/KA/RERA/1250/304/PR/230329/002280) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹39.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd. Banaswadi Branch (IFSC KARB0000126, a/c …7801). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub12 km
Kempegowda Int'l Airport18 km
Bellandur–Marathahalli belt19 km
Outer Ring Road / Manyata19 km
MG Road / city centre23 km
Electronic City28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Unique Construction.

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Unique Feronia?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 21 Sep 2026