Bangalore/Project record

K-RERA · the public record

VRR Fortuna

Bengaluru East · H. N. Vijaya Raghava Reddy & Co

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Aug 2018declared completionK-RERA registration · read 25 Oct 2026
388registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

2 BHK - 213, 3 BHK - 175, Total – 388
334

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

2.9registered acres

135.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for VRR Fortuna

K-RERA · PRM/KA/RERA/1251/446/PR/171027/000931

Project facts and comparisons

On the register

Declared completion31 August 2018
Land area11,634 sq m (2.9 acres)
Homes registered388
Tower/wing entries1
Unit mix334 × 2 BHK - 213, 3 BHK - 175, Total – 388

In context

Density135 homes per acre
Density in context96th percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units388Total inventory registered with K-RERA.
Official carpet area36,074 sqmTotal carpet area reported for the project.
Registered land area11,634 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.458Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)445Separate filed counts; these categories may overlap and are not added together.
Open-parking field52Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-09-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK - 213, 3 BHK - 175, Total – 388334100%36,074 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
VRR Fortuna18388445-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 388 official flat/unit rows, matching the 388 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK21385.0-89.0 sqm20.0 sqm213
3BHK175105.0-114.0 sqm20.0 sqm175

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
VRR Fortuna38885.0-114.0 sqm20.0 sqm388
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
103VRR Fortuna12BHK89.0 sqm20.0 sqm1
104VRR Fortuna13BHK111.0 sqm20.0 sqm1
105VRR Fortuna13BHK114.0 sqm20.0 sqm1
106VRR Fortuna12BHK89.0 sqm20.0 sqm1
107VRR Fortuna12BHK89.0 sqm20.0 sqm1
108VRR Fortuna13BHK110.0 sqm20.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 27 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Aug 2018, extended (Section 6 Extension) to 31 Aug 2019 — both dates have passed with no OC on file. The extension on file was granted on 26 Feb 2020 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/200226/000931) — it has been used, its deadline has also passed, and no further extension is recorded.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectK. Jeyaprakash Narayanan-2001LIC Colony, Srinagar Colony
ContractorH. N. Vijaya Raghava Reddy & Co.-19835th Block, Koramangala
Structural engineerV. G. Palaksha---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹36.9 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Karnataka Bank Ltd. Koramangala (IFSC KARB0000094, a/c …8401). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 3 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bellandur–Marathahalli belt4 km
Electronic City8 km
Whitefield IT hub9 km
MG Road / city centre13 km
Outer Ring Road / Manyata18 km
Kempegowda Int'l Airport33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vijaya Raghava.
Vijaya Raghava has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

VRR Golden Enclave Phase – I
No filings

Other RERA-registered projects in Chikkakannalli

Major developers building in Chikkakannalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.