HRERA · the public record
Group Housing Project
SECTOR-93, GURUGRAM · Signature Builders
Is this the right project?
Which unit should you choose?
Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.
See the report before you buy
Avoid bad decisions, only go for the best units.
Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.
Read the Project Review sample ↗From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗Free project details
Registration read 22 Oct 2026RERA details for Group Housing Project
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Group Housing Project records ₹53 L paid into and ₹52 L withdrawn from its RERA escrow account, with a latest recorded balance of ₹1 L.
₹53 L
into the escrow account
₹52 L
withdrawn
₹1 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q4 | 1 | 800 |
| 2025 Q1 | 0 | 800 |
| 2025 Q2 | 1 | 800 |
| 2025 Q3 | 1 | 800 |
| 2025 Q4 | 0 | 800 |
| 2026 Q1 | 0 | 800 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q4 | ₹19 L | ₹18 L | ₹0 L |
| 2025 Q1 | ₹4 L | ₹0 L | ₹4 L |
| 2025 Q2 | ₹15 L | ₹19 L | ₹0 L |
| 2025 Q3 | ₹14 L | ₹0 L | ₹14 L |
| 2025 Q4 | ₹1 L | ₹14 L | ₹1 L |
| 2026 Q1 | ₹0 L | ₹0 L | ₹1 L |
Builder Record
Signature Global has 6 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Group Housing Colony — declared 2021-05-31 · OC on record
- Group Houstng Project Ln — declared 2019-01-05 · OC on record
- Orchard Avenue 2 — declared 2024-09-30 · OC on record
- Orchard Avenue-3 — declared 2028-07-31
Location & Connectivity
The nearest of the listed job hubs is about 6 km in a straight line from the mapped location. Road distance and travel time will differ.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 17 km |
| Cyber City / DLF Cyber Hub | 18 km |
| Udyog Vihar | 18 km |
| IGI Airport, Delhi | 23 km |
| Connaught Place, Delhi | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.