Mumbai/Project record

MahaRERA · the public record

Bright Galaxy

Vasai East · BARKAAT BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

10units filed as unsoldInventory · 22 October 2026
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for Bright Galaxy

MahaRERA · P99000012924

Delivery and registration

When is the project declared for completion?

Bright Galaxy is registered with MahaRERA as P99000012924 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000012924
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Bright Galaxy record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 54 units carry one, and 10 of the 64 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
701/A350 sqftRs 12.50 lakh typical, over Rs 9.00 lakh to Rs 19.00 lakh29 filed · similar area (within 2%), same building

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In Bright Galaxy, every one of the 10 unsold units has filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 9 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
BRIGHT GALAXY 11G+731 Dec 2018

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for Bright Galaxy, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000059148309/08/2024Santosh kumar Bhimsen Soni vs M/s Barkaat Buildersorder passed
CC00600000059149310/08/2024Santosh kumar Bhimsen Soni vs M/s Barkaat Buildersorder passed
CC1240035206/10/2024Kamrunnisha Rafique Shah vs BARKAAT BUILDERSorder passed
CC1240037107/10/2024Niyaz Rafique Shah vs BARKAAT BUILDERSorder passed
CC1240063131/10/2024Mewalal Ramdhari Gupta vs BARKAAT BUILDERSorder passed
CC1240070808/11/2024Chandrakali Umesh Sharma vs BARKAAT BUILDERSorder passed
CC1240083620/11/2024Sumitra Harilal Gupta vs BARKAAT BUILDERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered14 Dec 2019issue of labour , unavailability labour ,sand
14 Dec 201931 Dec 2026Due to pandemic situation the construction is delayed.

Location, Land & Connectivity

Located at Vasai East, Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by SAGAR CITY, to the south by NALA, to the east by DHUMAAL NAGAR and to the west by NIRMAL TOWER. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 27 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ27 km
Powai / Hiranandani business park28 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai East

Matoshri Heights
declared completion Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
declared completion Nov 2026 · M M Enterprises
Apeksha Complex
declared completion Dec 2026 · Kothari Construction CO
Dhuri Infinity Block A Part Of Building Having Two Blocks I.e. A And B
Deregistered by MahaRERA · declared completion Dec 2026 · Sudhir Kashinath Dhuri
Nine Aura Construction
Deregistered by MahaRERA · declared completion Dec 2026 · Nine Aure Construction
Rashmi Star City Phase 2
declared completion Dec 2026 · Rashmi Realty Builders Pvt Ltd
More builders in Vasai East

Major developers building in Vasai East

More projects in Palghar

Other RERA-registered projects in Palghar

Bright Galaxy - Building NO. 2
declared completion Dec 2019 · Kamlesh Jayantilal Doshi
Brooklyn Park
declared completion Jul 2025 · Chandiwala Enterprises
Brooklyn Park Phase I
declared completion Nov 2020 · Ekta Parksville Homes Pvt. Ltd.
Brooklyn Park Phase II
declared completion Sep 2023 · Ekta Parksville Homes Pvt. Ltd.
Brooklyn Park Phase IV
declared completion Dec 2026 · Ekta Housing Private Limited
Building No 1: - Ayodhya Dham & Row House No 1, 2 & 3
declared completion Dec 2029 · Chintamani Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.