COMMERCIAL-2

Mumbai Suburban · S M ASSOCIATES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for COMMERCIAL-2

MahaRERA · P51700002138

Delivery and registration

When is the project declared for completion?

COMMERCIAL-2 is registered with MahaRERA as P51700002138 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700002138
Registered on31 Jul 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for COMMERCIAL-2 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

S M ASSOCIATES is the promoter of record on 6 projects registered with MahaRERA.

6projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for COMMERCIAL-2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
COMMERCIAL-21G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed statuses: 1 “Ongoing”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The High Court Of Judicature At Bombay1202019Ongoing
Filed description: ARBITRATION PETITION

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Kalyan Dombivali Municipal Corporation had abruptly cancelled our development agreement and therefore we have initiated Arbitration Proceedings against them in which there is order
31 Dec 201931 Dec 2021The Hon'ble High Court has given order to maintain status quo in civil suit arbitration appeal (ST) No. 11664 of 2019 between Kalyan Dombivli Municipal Corporation as Appellant and
31 Dec 202130 Jun 2024The Hon’ble High Court has given order to maintain status quo in civil suit arbitration appeal (ST) No.11664 of 2019 between Kalyan Dombivli Municipal Corporation as Appellant and

Location, Land & Connectivity

Located at Birla College Road, Andheri, Mumbai Suburban, 421301. Per the filed land record, the plot is bounded to the north by SURVEY NO 10 OF KALYAN, to the south by JUNCTION OF BHIWANDI - MURBAD ROAD , to the east by BHIWANDI - MURBAD ROAD and to the west by SURVEY NO 6 7 10 21. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 28 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every S M Associates project & its RERA track record →

Other RERA-registered projects in Kalyan

Midtown Twin Towers
declared completion Nov 2026 · Shirdi SAI Sheltors LLP
Heaven Enclave
declared completion Dec 2026 · Saxena Dreams Realty LLP
Krishna Leela
declared completion Dec 2026 · Shree Krishna Construction
Poddar Riviera Phase - II
Not filing quarterly progress reports · declared completion Dec 2026 · Poddar Housing And Development Limited
Shree Gajanan Fortune City
declared completion Dec 2026 · Arun Balu Patil
Tharwani Majestic Towers Phase II
declared completion Dec 2026 · Anil Hardasmal Tharwani
More builders in Kalyan

Major developers building in Kalyan

More projects in Thane

Other RERA-registered projects in Thane

Concept Arena
declared completion Dec 2023 · Concept Realty
Concorde Realty Kailash Building NO 11
declared completion Dec 2025 · Concorde Realty
Constrcution Of 2557 EWS Tenements At S.no.157/1,village Gotheghar,tal . Dist.-Thane Pmay Project
declared completion Jun 2028 · Maharashtra Housing And Area Development
Constructing EWS And LIG Tenements Under Pmay On S No 86 95 And 133 At Shirdhon Tal Kalyan Distthane
declared completion Mar 2027 · Maharashtra Housing AND Area Development
Continental Acropolis
declared completion Dec 2022 · Continental Builders AND Developers
Continental Futura
declared completion Mar 2028 · Continental Sidhant Reality

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.