Mumbai/Project record

MahaRERA · the public record

Prestige One

VILLAGE - BARAVE · GIRDHARI KALYANDAS LULLA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2027declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Prestige One

MahaRERA · P51700080828

Delivery and registration

When is the project declared for completion?

Prestige One is registered with MahaRERA as P51700080828 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

14months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51700080828
Registered on14 Jul 2025
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today14 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Prestige One record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-09-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Prestige One in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
Prestige One1G+18-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILLAGE - BARAVE , Near Shani Mandir, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by 18 metre wide road, to the south by Survey No 13 Hissa No 9, to the east by 15 metre wide road and to the west by 9 metre wide road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Midtown Twin Towers
declared completion Nov 2026 · Shirdi SAI Sheltors LLP
Heaven Enclave
declared completion Dec 2026 · Saxena Dreams Realty LLP
Krishna Leela
declared completion Dec 2026 · Shree Krishna Construction
Poddar Riviera Phase - II
Not filing quarterly progress reports · declared completion Dec 2026 · Poddar Housing And Development Limited
Shree Gajanan Fortune City
declared completion Dec 2026 · Arun Balu Patil
Tharwani Majestic Towers Phase II
declared completion Dec 2026 · Anil Hardasmal Tharwani
More builders in Kalyan

Major developers building in Kalyan

More projects in Thane

Other RERA-registered projects in Thane

Pride Heights
declared completion Dec 2027 · Pride Enterprises
Pride Land Residency
declared completion Dec 2024 · Sanadi Realty Properties Private Limited
Pride Living
declared completion Mar 2019 · Pride Life Spaces LLP
Pride Palms Majesty A1-B1 Phase 1
declared completion Dec 2018 · Larkins Realtors
Pride Park
declared completion Dec 2025 · Nikhil Rajesh Sukhramani
Pride Tower
declared completion Dec 2023 · Shree Gajanan Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.