Hari Vijay Lawns Building No.2

KHAMBALPADA · CREATIVE CONSTRUCTION

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Empire Solitaire

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Empire Solitaire Project Review · first page
First page of the complete sample.
30 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
9registered unitsMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Hari Vijay Lawns Building No.2

MahaRERA · P51700008121

Delivery and registration

When is the project declared for completion?

Hari Vijay Lawns Building No.2 is registered with MahaRERA as P51700008121 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700008121
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hari Vijay Lawns Building No.2 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

How many are filed as sold or booked?

In Hari Vijay Lawns Building No.2, 7 of 9 homes filed with MahaRERA are recorded as sold or booked, about 78%, and 2 are filed as unsold.

78%sold or booked

7 of 9 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit.

FloorUnitCarpetGovt reckoner value
Floor 11023,918 sqft (364 sqm)-
Floor 11044,241 sqft (394 sqm)-

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Hari Vijay Lawns Building No.2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 9 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
Hari Vijay Lawns1G+89-

Unit mix on the filing: 9 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DELAY DUE TO LOCKDOWN CAUSED COVID-19 VIRUS, CAUSING SHORTAGE OF LABOUR AND MATERIAL. ALL RELEVANT DOCUMENTS REQUIRED AS PER MAIL DATED 30/06/2021 HAVE BEEN UPLOADED IN RESPECTIVE

Location, Land & Connectivity

Located at KHAMBALPADA, 90FT ROAD BACKSIDE, Thane, Thane, 421201. Per the filed land record, the plot is bounded to the north by Land of Manohar Choudhary, to the south by 12 mtr Wide Road, to the east by Land of Krishna Bhoir and to the west by 24 mtr Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 24 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park24 km
Andheri MIDC / SEEPZ27 km
Chhatrapati Shivaji Int'l Airport29 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district38 km
Nariman Point / Fort44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Shanu Majestic
declared completion Dec 2026 · Fortune Group Of Construction
Balaji Annex
declared completion Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders
Leela Shankar Residency
declared completion Dec 2026 · Ekveera AAI Construction
Ram Janaki
declared completion Dec 2026 · Shree Ganesh Enterprises
UMA Lambodar Heights
Not filing quarterly progress reports · declared completion Dec 2026 · Shree RAJ Properties Developers
Aditya Heights
declared completion Dec 2026 · Ashapura Developers
More builders in Dombivli East

Major developers building in Dombivli East

More projects in Thane

Other RERA-registered projects in Thane

Harihar Darshan
declared completion Dec 2026 · Borgaonkar Realty
Harikunj Enclave
declared completion Aug 2025 · Samir Shrinivas Kale
Hariom Elite
declared completion Dec 2029 · Hariom Apr Realty
Hariom NXT
declared completion May 2024 · Hariom Enterprise
Harisha
declared completion Jun 2028 · Omkar Manik Mhatre
Harishree Celestial-1
declared completion Dec 2028 · Harishree Creations

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.