LIJJAT JAMUNA CHS LTD

MULUND EAST · ASHWINI AJIT KARANDIKAR

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for LIJJAT JAMUNA CHS LTD

MahaRERA · P51800005872

Delivery and registration

When is the project declared for completion?

LIJJAT JAMUNA CHS LTD is registered with MahaRERA as P51800005872 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005872
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LIJJAT JAMUNA CHS LTD record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LIJJAT JAMUNA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
JAMUNA CHS1G+830 Jun 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for LIJJAT JAMUNA CHS LTD, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019535223/12/2020UDAY MANTRI vs M/s Ashwini Enterprisesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020Due to poor response for booking and paucity of funds the work got delayed. We are negotiating with some banks/NBFC for construction finance and if we are able to get sanction fr
31 Dec 202031 Dec 2022Due to Pandemic
31 Dec 202231 Dec 2023Project is almost complete and 50% payment for Parking Systems is also done. Installation of the System should start from August,2023. All the compliances necessary for obtaining O

Location, Land & Connectivity

Located at MULUND EAST, SANE GURUJI NAGAR, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by CTS 1123A-1-1, to the south by CTS 1124-A, to the east by CTS 1123B and to the west by CTS 1123A-1-2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Mithagar Road Ekta Chsl
declared completion Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
declared completion Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
declared completion Dec 2026 · Omsai Developers
Jvms Monica Gardens
declared completion Dec 2026 · JVM Spaces
Mahatma Jyotiba Phule CHS LTD
declared completion Dec 2026 · Tridevh Construction Company
OM Mayuresh
declared completion Dec 2026 · M/s Keytech
More builders in Mulund East

Major developers building in Mulund East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Linkbay Residences Phase I
declared completion Oct 2028 · Portsmouth Buildcon Private Limited
Linkpark
declared completion Oct 2026 · Adarsh Industrial Estate Private Limited
Live Well Chs Ltd
declared completion Dec 2029 · Icon Constructions
Livsmart Kurla
declared completion Mar 2028 · D. K. Realty Pvt. Ltd.
LK Aura
declared completion Sep 2029 · L K Infracon LLP
LK Elegance
declared completion Mar 2028 · L K Infracon LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.