Mulund Ravi Kailash 16th, 17th, 18th floor

Tata Colony Junction · M PATANKAR BUILD CONS PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
27 May 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Mulund Ravi Kailash 16th, 17th, 18th floor

MahaRERA · P51800018681

Delivery and registration

When is the project declared for completion?

Mulund Ravi Kailash 16th, 17th, 18th floor is registered with MahaRERA as P51800018681 and the promoter has declared completion for 27 May 2022.

27 May 2022

declared completion

53months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800018681
Registered on27 Nov 2018
Promoter-declared completion27 May 2022
Current statusCertificate Signed
Against todayabout 53 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mulund Ravi Kailash 16th, 17th, 18th floor record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

M PATANKAR BUILD CONS PRIVATE LIMITED is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Mulund Ravi Kailash 16th, 17th, 18th floor in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Mulund Ravi Kailash 16th to 18th floor1G+230 Nov 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered27 May 2022The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprec

Location, Land & Connectivity

Located at Tata Colony Junction, Navghar Road, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by Navghar Road, to the south by Vikram Society, to the east by TATA colony road and to the west by Ravi Raj Society. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Mithagar Road Ekta Chsl
declared completion Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
declared completion Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
declared completion Dec 2026 · Omsai Developers
Jvms Monica Gardens
declared completion Dec 2026 · JVM Spaces
Mahatma Jyotiba Phule CHS LTD
declared completion Dec 2026 · Tridevh Construction Company
OM Mayuresh
declared completion Dec 2026 · M/s Keytech
More builders in Mulund East

Major developers building in Mulund East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Mulund Shriram CO-Operative Housing Society Limited
declared completion Dec 2030 · Razo Developers
Muncipal Employees Deep Darshan CO Operative Housing Society Limited
declared completion Dec 2025 · Saikaran Buildtech LLP
Municipal Employees Akanksha Chsl
declared completion Jun 2023 · Konark Structural Engineers Private Limi
Municipal Staff Mandar Chsl
declared completion Nov 2028 · Ossia Developers
Municipal Staff Sahayog CHS LTD
declared completion Dec 2029 · Konark Structural Engineers Private Limi
Munisuvrat Chhaya
declared completion Dec 2029 · Vira Group Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.