POORVA MEGHNANDA CHS LTD

Mumbai Suburban · Varadvinayak Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for POORVA MEGHNANDA CHS LTD

MahaRERA · P51800005599

Delivery and registration

When is the project declared for completion?

POORVA MEGHNANDA CHS LTD is registered with MahaRERA as P51800005599 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005599
Registered on11 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for POORVA MEGHNANDA CHS LTD record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Varadvinayak Developers is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for POORVA MEGHNANDA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
POORVA MEGHNANDA CHS LTD1G+1930 Jun 2018

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for POORVA MEGHNANDA CHS LTD, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017173501/12/2019RAJEEV PRAHDAN vs Mr. Mandar Vaidyaorder passed
CC00600000042940626/02/2024Rahul Moreshwar Nachane vs Mr. Mandar Vaidyaorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020CC could not be issued for want of clarifications on Reg. No. 33 (7) (B), Building is proposed for 19 floors and is completed up to 18th floor with 95% work completed and only one
30 Apr 202030 Apr 2020Additional extension of construction area as approved by M.C.G.M. over and above the earlier sanctioned plans.
30 Apr 202031 Dec 2021AI Mr. Mandar Vaidya, Partner of “Varadvinayak Developers” do hereby declare that the project “Poorva Meghnanda CHS LTD” is registered with MahaRERA vide Registration Number “P5180

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by G V SCHEME ROAD NO 1, to the south by G V SCHEME ROAD NO 2, to the east by GURBHAKTI CHS and to the west by L T ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Mithagar Road Ekta Chsl
declared completion Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
declared completion Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
declared completion Dec 2026 · Omsai Developers
Jvms Monica Gardens
declared completion Dec 2026 · JVM Spaces
Mahatma Jyotiba Phule CHS LTD
declared completion Dec 2026 · Tridevh Construction Company
OM Mayuresh
declared completion Dec 2026 · M/s Keytech
More builders in Mulund East

Major developers building in Mulund East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

PR Heights
declared completion Mar 2025 · Pankhi Reliable Developers LLP
Prabhat
declared completion Dec 2025 · Shivam Parivar Developers PVT LTD
Prabhat Kunj
declared completion Jun 2025 · Lakshmiconstruction
Prabhat Residency
declared completion Dec 2025 · Not Available
Prabhu Krupa
declared completion Dec 2027 · Mehul Kirit Mehta
Prabhu Plaza
declared completion Jun 2026 · M/S United Housing Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.