Mumbai/Project record

MahaRERA · the public record

Redevelopment of Nirav CHSL

DAHISAR WEST · NAVIN KARAMSHI SHAH

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Empire Solitaire

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Empire Solitaire Project Review · first page
First page of the complete sample.
12units filed as unsoldInventory · 18 October 2026
31 Dec 2024declared completionMahaRERA registration · read 18 Jul 2026
33registered unitsMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Redevelopment of Nirav CHSL

MahaRERA · P51800031804

Delivery and registration

When is the project declared for completion?

Redevelopment of Nirav CHSL is registered with MahaRERA as P51800031804 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800031804
Registered on12 Nov 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Redevelopment of Nirav CHSL record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

How many are filed as sold or booked?

In Redevelopment of Nirav CHSL, 2 of 14 homes filed with MahaRERA are recorded as sold or booked, about 14%, and 12 are filed as unsold.

14%sold or booked

2 of 14 homes

₹2.00 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹2.00 Cr (about 100%) is recorded as collected and ₹0 as receivable. The registration lists 33 homes; this inventory lists 14. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit.

FloorUnitCarpetGovt reckoner value
Floor 1B - 102368 sqft (34.2 sqm)₹53.40 Lakh
Floor 2B - 201637 sqft (59.14 sqm)₹92.15 Lakh
Floor 2B - 202368 sqft (34.2 sqm)₹53.40 Lakh
Floor 4B - 401521 sqft (48.42 sqm)₹92.15 Lakh
Floor 5B - 501637 sqft (59.14 sqm)₹92.15 Lakh
Floor 5B - 503394 sqft (36.61 sqm)₹57.17 Lakh
Floor 7B - 703394 sqft (36.61 sqm)₹57.17 Lakh
Floor 8A - 801521 sqft (48.42 sqm)₹75.59 Lakh
Floor 8B - 801637 sqft (59.14 sqm)₹92.15 Lakh
Floor 8B - 802368 sqft (34.2 sqm)₹53.40 Lakh
Floor 8B - 803394 sqft (36.61 sqm)₹57.17 Lakh
Floor 9A-901521 sqft (48.42 sqm)₹75.59 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Redevelopment of Nirav CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 October 2026

What the filings record, home by home

Read from MahaRERA on 18 October 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 2 homes carry one, and 12 of the 14 are recorded unsold.

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 33 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
WING A1G+8931 Dec 2024
WING B1G+82431 Dec 2024

Unit mix on the filing: 33 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Redevelopment of Nirav CHSL, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000021013822/02/2022Hemant R Patel vs Nirav Co-operative Housing Society Ltd.order passed

Legal & Litigation

The promoter has declared 10 court cases on this project to MahaRERA. Filed statuses: 6 “Ongoing”; 4 “PENDING” (filed description; status field empty). These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Dindoshi City Civil Court7342020Ongoing
Filed description: PENDING
Dindoshi City Civil Court7352020Ongoing
Filed description: PENDING
Dindoshi City Civil Court7362020Ongoing
Filed description: PENDING
Dindoshi City Civil Court7632020Ongoing
Filed description: PENDING
Dindoshi City Civil Court7372020Ongoing
Filed description: PENDING
High Court BombayAO/225/20212021Status not supplied
Filed description: PENDING
High Court BombayAO/238/20212021Status not supplied
Filed description: PENDING
High Court BombayAO/322/20212021Status not supplied
Filed description: PENDING
High Court BombayAO/331/20212021Status not supplied
Filed description: PENDING
City Civil Court, Dindoshi2026942020Ongoing
Filed description: Notice of Motion

Location, Land & Connectivity

Located at DAHISAR WEST, VAMANRAO BHOIR MARG, Andheri, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by GOVERNMENT STAFF QUARTERS, to the south by 833B, to the east by 874A and to the west by GOVERNMENT STAFF QUARTERS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 14 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahisar East

Jeandveekedarnath
declared completion Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
declared completion Dec 2026 · Harshal Enterprises
Swayam Niketan
declared completion Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · declared completion Dec 2026 · Ashapura Housing Private Limited
Amber Heights
declared completion Dec 2026 · Ghanshyam Enterprises
Ashtha Sharon Dahisar West
declared completion Dec 2026 · Indo Build Enterprise
More builders in Dahisar East

Major developers building in Dahisar East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Redevelopment Of OB Swarganga Chsl CTS No 154 Pt Survey No 383 Pt Chaitanya Ngr Santacruz E Mum 55
declared completion Dec 2021 · A A Estates Pvt Ltd
Redevelopment OF OM Manikanta Chsl
declared completion Dec 2027 · Pranav Constructions Limited
Redevelopment Of Parvatikunj Chsl
declared completion Dec 2023 · Yash Om Developers
Redevelopment OF Pearl Palace
declared completion Sep 2027 · Pranav Constructions Limited
Redevelopment OF Plot NO. 212
declared completion Feb 2025 · Pranav Constructions Limited
Redevelopment Of Prateeksha CHS Ltd
declared completion Sep 2018 · Ashiana Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.