Sumer Trinity Vertical Phase-I

Prabhadevi · Sumer Builders

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Sumer Trinity Vertical Phase-I

MahaRERA · P51900017371

Delivery and registration

When is the project declared for completion?

Sumer Trinity Vertical Phase-I is registered with MahaRERA as P51900017371 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900017371
Registered on09 Aug 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Promoter record

What else is this promoter on record for?

Sumer Builders is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sumer Trinity Vertical Phase-I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+36.

BuildingWingsFloorsDeclared completion
Vertical1G+36-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 6 “Pending”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Maharashtra Revenue Tribunal5902014Status not supplied
Filed description: Pending
High Court Mumbai28812015Status not supplied
Filed description: Pending
High Court Mumbai1652013Status not supplied
Filed description: Pending
High Court Mumbai1232013Status not supplied
Filed description: Pending
High Court Mumbai29862015Status not supplied
Filed description: Pending
High Court Mumbai3792017Status not supplied
Filed description: Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprec

Location, Land & Connectivity

Located at Prabhadevi, New Prabhadevi Marg, Ward GSouth, Mumbai City, 400025. Per the filed land record, the plot is bounded to the north by Jiwba Atmaram Raul Road, to the south by Suryodaya CHS, to the east by Crown Mill Compound and to the west by New Prabhadevi Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 1 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Lower Parel / Worli business district1 km
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Prabhadevi

25 South Tower A 11th To 47th Floor
declared completion Dec 2026 · Twenty Five South Realty Limited
25 South Tower A Upto 10th Floor
declared completion Dec 2026 · Twenty Five South Realty Limited
25 South - Central Tower
Deregistered by MahaRERA · declared completion Dec 2028 · Twenty Five South Realty Limited
Kshitij Omkar
declared completion Nov 2030 · Omkar CHS Ltd
Vakratunda Crest
declared completion Dec 2030 · Inclineestate Properties LLP
Naia
declared completion Dec 2030 · Prabhadevi Developer Private Limited
More builders in Prabhadevi

Major developers building in Prabhadevi

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Sumit Atulyam
declared completion Dec 2024 · Sumit Matunga Builders Private Limited
Sumit Lata
declared completion Jan 2021 · Sumit Snehashish Venture
Sumukh Plaza
declared completion Dec 2025 · Dharmesh Construction CO.
Sunshine Infinity
declared completion Dec 2019 · SQ Infrastructure Private Limited
Sunstone Epitome
declared completion Dec 2028 · Sunstone Constructions
Supreme Melange
declared completion Jun 2024 · Supreme Ventures LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.