Mumbai/Project record

MahaRERA · the public record

The Square

Jawar Nagar Goregaon · Geopreneur Corp Pvt. Ltd.

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2028declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for The Square

MahaRERA · P51800018189

Delivery and registration

When is the project declared for completion?

The Square is registered with MahaRERA as P51800018189 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

20months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800018189
Registered on15 Oct 2018
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today20 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Square record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for The Square in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
The Square1G+22-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2028we would like to draw your attention to the fact that we obtained the Intimation of Disapproval (IOD) for the residential project on 14-02-2017. Subsequently, we received the first

Location, Land & Connectivity

Located at Jawar Nagar Goregaon, SV Road, Borivali, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by Petrol Pump and Aarey Road, to the south by Anant Niwas, to the east by Uday CHSL and to the west by SV Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Vallabh Krupa Chsl
declared completion Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
declared completion Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
declared completion Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
declared completion Dec 2026 · Dhariwal Developers Private Limited
Asmi Legacy
declared completion Dec 2026 · Asmi Developers
Building No.9 - Phase II
declared completion Dec 2026 · Kalindi Estate Developers
More builders in Goregaon West

Major developers building in Goregaon West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

THE Umiya Mahal Flat Owners Chsl
declared completion Jun 2023 · Rishi Metro
THE Vibe
declared completion Jun 2028 · Sahakar Builders & Developers
THE Views
declared completion Dec 2026 · Agnel Developers LLP
THE Views II
declared completion Dec 2026 · Agnel Developers LLP
THE VUE
declared completion Dec 2029 · Not Available
The Waterfront
declared completion Aug 2026 · M/s Orbit Developers

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.