TRIVENI LOTUS

UMROLI · Trivenilandspace

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
01 Aug 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for TRIVENI LOTUS

MahaRERA · P99000008136

Delivery and registration

When is the project declared for completion?

TRIVENI LOTUS is registered with MahaRERA as P99000008136 and the promoter has declared completion for 01 Aug 2022.

01 Aug 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000008136
Registered on18 Aug 2017
Promoter-declared completion01 Aug 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TRIVENI LOTUS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TRIVENI LOTUS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
WING A1G+3-
B WING1G+3-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for TRIVENI LOTUS, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000036465206/03/2023JAYESH VINOD PARMAR vs Ashok Arvind Jethwaorder passed
CC1260390124/06/2026JAYESH VINOD PARMAR vs Trivenilandspacepending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020While registered the Project partners estimate very short period for completion of the Project. In view of that we are request to Your Honor for grant of extension. Further, partne
31 Jul 202031 Jul 2020Since the partner in the firm were changed. New partners are dedicatly working for the completion of project. they got very few time to complete the project.
31 Jul 202001 Feb 2022Due to COVID 2019 there was lockdown for many months. Further there were many restriction i.e non operarion of local train, etc. Hence we could not able to do work.

Location, Land & Connectivity

Located at UMROLI, MAHARASHTRA, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by BUILDING NO 3 TYPE C, to the south by 12 MT WIDE ROAD, to the east by GUT NO 153 and to the west by BUILDING NO 2 TYPE F. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 71 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ71 km
Powai / Hiranandani business park73 km
Chhatrapati Shivaji Int'l Airport75 km
Bandra Kurla Complex (BKC)78 km
Lower Parel / Worli business district85 km
Nariman Point / Fort93 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shiv Krupa
declared completion Oct 2026 · Shivaay Realty
V Square Arcade
declared completion Oct 2026 · V Square
Nisarg Shrushti Phase-2
declared completion Nov 2026 · Arvel Realtors
Aloha
declared completion Nov 2026 · SEA Crests Buildcon LLP
Paramount Enclave Phase -1
declared completion Nov 2026 · Kavita Realty Housing LLP
Solitaire Park
declared completion Nov 2026 · Park Solitaire Lifespaces LLP
More builders in Palghar

Major developers building in Palghar

More projects in Palghar

Other RERA-registered projects in Palghar

Tulip Residency
declared completion Dec 2018 · Brright Realtors
Tulip Residency
declared completion Dec 2029 · Kohinoor Buildcon
Tulsi Dham
declared completion Nov 2021 · P & V Developers
Tulsi Heights
declared completion Dec 2022 · Jignesh Omprakash Vyas
Tulsi Heights
declared completion Dec 2030 · Sharp Realtors
Umiya Villas
declared completion Mar 2029 · Umiya Villas

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.