68units filed as unsoldInventory · 22 October 2026
29 Dec 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for VRINDHAVAN COMPLEX

MahaRERA · P99000016354

Delivery and registration

When is the project declared for completion?

VRINDHAVAN COMPLEX is registered with MahaRERA as P99000016354 and the promoter has declared completion for 29 Dec 2026.

29 Dec 2026

declared completion

2months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000016354
Registered on08 May 2018
Promoter-declared completion29 Dec 2026
Current statusCertificate Signed
Against today2 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VRINDHAVAN COMPLEX record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 22 units carry one, and 68 of the 146 are recorded unsold. Since we started watching this ledger, 1 unit has moved out of the unsold list, most recently on 22 October 2026.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
BLDG NO 3 A WING-A-001286 sqftRs 11.41 lakh typical, over Rs 9.00 lakh to Rs 12.33 lakh9 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today.

In VRINDHAVAN COMPLEX, 48 of the 68 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 67 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BLDG NO 1 A WING1G+12-
BLDG NO 1 B WING1G+7-
BLDG NO 1 C WING1G+7-
BLDG NO 2 A WING1G+7-
BLDG NO 2 B WING1G+4-
BLDG NO 2 C WING1G+4-
BLDG NO 3 A WING1G+4-
BLDG NO 3 B WING1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2026unavailability of material Due to covid-19 pandemic and shortage of labors

Location, Land & Connectivity

Located at PARASNATH NAGARI, UMROLI STATION ROAD, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by 19 45027 N 72 454443 E, to the south by 19 455868 N 72 454460 E, to the east by 19 455949 N 72 454560 E and to the west by 19 445940 N 72 454350 E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 71 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ71 km
Powai / Hiranandani business park73 km
Chhatrapati Shivaji Int'l Airport75 km
Bandra Kurla Complex (BKC)78 km
Lower Parel / Worli business district85 km
Nariman Point / Fort93 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shiv Krupa
declared completion Oct 2026 · Shivaay Realty
V Square Arcade
declared completion Oct 2026 · V Square
Nisarg Shrushti Phase-2
declared completion Nov 2026 · Arvel Realtors
Aloha
declared completion Nov 2026 · SEA Crests Buildcon LLP
Paramount Enclave Phase -1
declared completion Nov 2026 · Kavita Realty Housing LLP
Solitaire Park
declared completion Nov 2026 · Park Solitaire Lifespaces LLP
More builders in Palghar

Major developers building in Palghar

More projects in Palghar

Other RERA-registered projects in Palghar

Vrundavan Heights
declared completion Jan 2024 · Pareshkumar Sevantilal Modi
Whitehill Residential
declared completion Dec 2026 · Riva Realtors
Wollywood Gold I
declared completion Jul 2022 · Nirvana Lifestyle Homes LLP
Wollywood Phase II
declared completion Dec 2026 · Nirvana Lifestyle Ventures
Wollywood Phase III
declared completion Dec 2026 · Nirvana Lifestyle Ventures
Wollywood Phase V
declared completion Dec 2026 · Nirvana Lifestyle Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.