The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.
Building
Wings
Floors
Declared completion
70 WEST AVENUE
1
G+12
30 Dec 2022
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
From
Extended to
Stated reason
as registered
30 Dec 2023
Our project is on the verge of getting physically completed in all aspects, which is indicated by the latest Form 1 Project Architect Certificate that we have attached with this ap
30 Dec 2023
30 Sep 2024
a) Our Project- ‘70 WEST AVENUE’ bearing Reg. No. P52100017946 had its initial registration valid till 31st December, 2021 which was extended for 6 months ending 30th June, 2022 vi
Location, Land & Connectivity
Located at Erandawane, Karve Raod, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by F P No 70 3B, to the south by Road, to the east by F P No 70 2A and to the west by FP No70 1A. These are the boundaries as recorded in the filed land record.
Free · Watch this project
We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.
Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.