Plotted Development Intelligence · Borhadewadi · Pune

DURVA PARK PLOT E

P52100034345 · BORHADEWADI · promoter Rajesh Eriappa Gowda

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

DURVA PARK PLOT E is registered with MahaRERA as P52100034345 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034345
Registered on04 Apr 2022
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DURVA PARK PLOT E record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Rajesh Eriappa Gowda is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In DURVA PARK PLOT E, 0 of 30 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 30 remain available.

0%sold

0 of 30 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DURVA PARK PLOT E in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BORHADEWADI, BORHADEWADI MOSHI, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by LAND OF MR SASTE KALE HONRAO, to the south by MR RAJESH ERE GOWDA, to the east by LAND OF MR AMIT MORE AND MR NIRAJ JADHAV and to the west by 12 M WIDE D P ROAD. These are the boundaries as recorded in the filed land record.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the plot to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which plot to ask for · Drawings Report

The plot-level read: which parts of the layout to prefer and which to avoid, what the approved layout puts against each boundary — roads, drains, open land — and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

A thin filing

The crawled listing for DURVA PARK PLOT E shows only one approved drawing — not enough drawn material for a useful unit-level read, and we would rather tell you that than sell you a thin report. The register record above is what this filing carries.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rajesh Eriappa Gowda is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Rajesh Eriappa Gowda

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Durvankur Residency
declared completion Dec 2023 · JAI Ganesh Construction
Durvankur Residency C Wing
declared completion May 2026 · Durvankur Developers
Durvankur Srushti
declared completion Dec 2025 · Durvankur Vastunirmiti Private Limited
Dutt Smriti Aangan
declared completion Dec 2019 · Kirti Uttamchand Jeswani
Dwaarka Avenue
possession by Mar 2027 · Monarch Developers
Dwaarka World Mhada Buildings
declared completion Dec 2025 · Shivpratap Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026