Pune/Project record

MahaRERA · the public record

INDRAPRASTHANAGARI-PHASE 1

wadgaon · D.B.DEVELOPERS LTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for INDRAPRASTHANAGARI-PHASE 1

MahaRERA · P52100014352

Delivery and registration

When is the project declared for completion?

INDRAPRASTHANAGARI-PHASE 1 is registered with MahaRERA as P52100014352 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100014352
Registered on24 Nov 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INDRAPRASTHANAGARI-PHASE 1 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INDRAPRASTHANAGARI-PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
INDRAPRASTHANAGARI A -PHASE 11G+815 Aug 2022
INDRAPRASTHANAGARI-B PHASE 11G+815 Aug 2022
INDRAPRASTHANAGARI-C PHASE 11G+815 Aug 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for INDRAPRASTHANAGARI-PHASE 1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000005382026/12/2019DINESH KUMAR AND GAYATRI RAJBALLI PRASAD vs D B DEVELOPERS LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 7 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020The promoter has completed the project around 65% but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. It
31 Dec 202031 Dec 2020WE HAVE A DELAY OF SHORT FUND PROBLEM FOR COMPLETION THE CONSTRUCTION ACTIVITIES IN SITE, WE ARE SURE THAT COMPLETED ALL ACTIVATE BEFOUL DELAY DATE .
31 Dec 202015 Aug 2022The promoter has completed the project around 66 % but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. I
15 Aug 202231 Dec 2022The said extension for project completion to the promoter may be granted till 31/12/2022 so that shall be completed and possession shall be given to the unit purchasers in the said
31 Dec 202231 May 2023we have done almost 95% Building work completed I need some more time for compilation certificate and society formation formality so I request you please give me some time
31 May 202331 Oct 2023NEED SOME MORE TIME FOR SOCETY FORMATION AND BUILDING OUTSIDE WORK COMPLITION WORK
31 Oct 202330 Jun 2024Although we have completed 98% of the project, we need more time for work and occupancy certificate, we request you to give us some time.

Location, Land & Connectivity

Located at wadgaon, MIDC Road, Pune City, Pune, 412106. Per the filed land record, the plot is bounded to the north by 18 M ROAD, to the south by SERVE NO 107 PART, to the east by SERVE N0 107 PART and to the west by 12M ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 84 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park84 km
Baner–Balewadi belt89 km
Pune Junction / city centre100 km
Pune Int'l Airport (Lohegaon)101 km
Kharadi / EON IT Park105 km
Magarpatta / Hadapsar IT105 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
declared completion Oct 2026 · Oneness Realtors
Samarth Heights
declared completion Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
declared completion Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
declared completion Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
declared completion Dec 2026 · Luxuriant Group
Surya Heights
declared completion Dec 2026 · SSB Developer
More builders in Vadgaon Maval

Major developers building in Vadgaon Maval

More projects in Pune

Other RERA-registered projects in Pune

Indrashri
declared completion Jun 2027 · B U Bhandari Buildcon LLP
Indrayani Puram
declared completion Dec 2024 · Shivkrupa Developers
Indrayani Riverview Residency
declared completion Jun 2026 · Shreenath Developers
Indrayani Terreses
declared completion Jun 2024 · Shivratna Associates
Indrayani Tower
declared completion Dec 2027 · Nandkumar Pandharinath Kurhade
Indrayani Vatika F Building
declared completion Jun 2025 · Sanskruti Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.