Bangalore/Project record

K-RERA · the public record

ADITI TROPICA

Bengaluru East · ADITI TROPICA

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Dec 2019declared completionK-RERA registration · read 25 Oct 2026
72registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

1.0registered acres

72.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for ADITI TROPICA

K-RERA · PRM/KA/RERA/1251/446/PR/180319/001089

Project facts and comparisons

On the register

Declared completion31 December 2019
Land area4,009 sq m (1.0 acres)
Homes registered72
Tower/wing entries2

In context

Density72.7 homes per acre
Density in context45th percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units72Total inventory registered with K-RERA.
Registered land area4,009 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)85Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-11-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block A43840-
Block B43445-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 34 official flat/unit rows vs 72 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK26848.2-1,288.1 sqft3.0-1,000.0 sqft26
3BHK81,137.2-1,309.7 sqft6.0-668.0 sqft8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block A34848.2-1,309.7 sqft3.0-1,000.0 sqft34
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G7Block A02BHK930.0 sqft465.0 sqft1
G002Block A02BHK953.1 sqft3.0 sqft1
G003Block A02BHK970.6 sqft519.0 sqft1
G4Block A02BHK884.8 sqft5.0 sqft1
G005Block A03BHK1,309.7 sqft6.0 sqft1
G006Block A03BHK1,309.7 sqft7.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 14 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2019, extended (Section 6 Extension) to 31 Dec 2020 — both dates have passed with no OC on file. The extension on file was granted on 11 Jul 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/220711/001089) — it has been used, its deadline has also passed, and no further extension is recorded.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Ravi lakshmi narayana vs Aditi Tropica. Request RERA intervention to take action on Developers along with 12% interest on entire sale consideration from 25/03/2015 till handover of the schedule propertyAUTHORITY28/05/2025
Ravi lakshmi narayana vs ADITI TROPICAcompletion of construction within 60 daysAUTHORITY23/03/2026
Prapanch Ramamoorthy vs Aditi TropicaDelay in possession, help in recovering the refundAUTHORITY20/05/2025
Ankit Singh vs ADITI TROPICAI want full refund with interest.AUTHORITY10/06/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/191205/0003223
05-12-2019
Want refund of the amount paid to the projectADITI TROPICADISPOSED AO
CMP/210121/0007481
21-01-2021
Delay in possession, help in recovering the refundADITI TROPICADISPOSED AUTHORITY BENCH4
CMP/210804/0008209
04-08-2021
Fraud and DelayADITI TROPICADISPOSED AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectHANUMESH GONHAL-200911th Main, 3rd Block
Structural engineerSyed Khadar---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹16.0 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: YES BANK HSR Layout (IFSC YESB0000535, a/c …0631). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata5 km
Bellandur–Marathahalli belt10 km
Whitefield IT hub15 km
Electronic City18 km
Kempegowda Int'l Airport24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Aditi Tropica.
6 complaints on the K-RERA register against Aditi Tropica in Bangalore.

Other RERA-registered projects in Fraser Town

Sobha Sentosa Phase 2 Wing 5 And 6
Sobha Sentosa Phase 3 Wing 3 And 4
Sobha Windsor Phase 3 Wing 6, 7 And 8

Major developers building in Fraser Town

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.