Bangalore/Project record

K-RERA · the public record

ISHA SERENE

Anekal · Mars Builders and Developers

Project Review · example purchase

Spending a few crores on a plot? ₹4,999 to check what you’re buying.

Check what the plans put beside your plot, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2026declared completionK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

ODD
37

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for ISHA SERENE

K-RERA · PRM/KA/RERA/1251/308/PR/091122/005431

Project facts and comparisons

On the register

Declared completion31 December 2026
Unit mix37 × ODD

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan numberSTRRPA/TP/LAO/08/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date30-10-2021
Project start date30-10-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
ODD37100%4,858 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

10 of 27 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: Electricity Permission Letter
Water & sewage (BWSSB/KWSSB)Document listed: Water Permission Letter
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSSN & ASSOCIATES2088072020Bengaluru Urban, Karnataka - 560070
EngineerBALAJI K.NBCC/BL-3.6/E-0345/21-222022Tiruvallur, Tamil Nadu - 631202

Builder track record

RERA filing

Mars Builders has 2 other K-RERA-registered projects in our records (average reported construction progress 100%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Canara Bank Banashankari 2nd stage IFSC Code : CNRB0010478 Pin Code : 560070. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 16 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City16 km
Bellandur–Marathahalli belt25 km
Whitefield IT hub30 km
MG Road / city centre31 km
Outer Ring Road / Manyata38 km
Kempegowda Int'l Airport54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mars Builders.
Mars Builders has 3 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Mars Builders in Bangalore.

Other projects by this builder in Bangalore

Mars THE Planet
Filing overdue · 100% built · 35% sold

Other RERA-registered projects in BEML Cooperative Society Layout

Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5

Major developers building in BEML Cooperative Society Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.