Bangalore/Project record

K-RERA · the public record

Warrior Central Bay

Bengaluru North · Y V Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
26units not bookedof 80 · Q1 2026 filing
31 Oct 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Oct 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3BHK
48
2BHK
32

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.3registered acres

59.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/091123/006404

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 October 2025
Land area5,463 sq m (1.3 acres)
Homes registered80
Tower/wing entries2
Unit mix48 × 3BHK, 32 × 2BHK

In context

Density59.3 homes per acre
Density in context32nd percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units80Total inventory registered with K-RERA.
Official carpet area8,185 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area11,282 sqmUseful scale context when comparing density and project cost.
Registered land area5,463 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.498Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)88Separate filed counts; these categories may overlap and are not added together.
Covered-parking field88Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBIAAPA/TP/CC/261/2022-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date23-05-2023
Project start date01-10-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK4860%4,709 sqm
2BHK3240%1,980 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block A3525314.55 m
Block B3283514.55 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 80 official flat/unit rows, matching the 80 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK4965.9-102.0 sqm53.5-84.2 sqm49
2 BHK3160.8-65.9 sqm50.7-53.5 sqm31

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block A5260.8-102.0 sqm50.7-84.2 sqm52
Block B2865.9-95.1 sqm53.5-78.2 sqm28
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G1Block A03 BHK99.2 sqm78.1 sqm1
G2Block A03 BHK102.0 sqm84.2 sqm1
G3Block A03 BHK100.0 sqm81.2 sqm1
G4Block A03 BHK94.0 sqm77.9 sqm1
G5Block A03 BHK99.2 sqm78.1 sqm1
G6Block A03 BHK102.0 sqm84.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 10 of 28 compliance document slots are filed as under process / not yet usable: Board Resolution for Authorized Signatory/Certificate of Authorization, Certificate from Chartered Account, Commencement Certificate, Water Permission Letter, Urban Land Ceiling and more.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
KSPCB- PCB (10 Acres to 125 Acres)Approved19-05-2023KSPCB NOC 190522023.pdf
KPTCL- BESCOMApproved12-10-2023BESCOM NOC Hosahalli 121023.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantKorrapadu Chennareddy2353242019Anantapur, Andhra Pradesh - 515465
EngineerKiran KumarBCC/BL-3.6/SE/0331/2019-202019Bengaluru Urban, Karnataka - 560087
ArchitectSurendra KumarCA/2010/504322022Bengaluru Urban, Karnataka - 560024
ContractorY V Constructions-2020Bengaluru Urban, Karnataka - 560092

Builder track record

RERA filing

Constructions has 19 other K-RERA-registered projects in our records (average reported construction progress 90%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹3.81 Cr collected from buyers, ₹2.67 Cr withdrawn from the project's escrow account.

Construction progress90% → 100% (+10 pts)
Units sold/booked as registered54/80 (68%)
Buyer collections in available QPRs₹15.16 Cr
Escrow withdrawals in available QPRs₹10.61 Cr (0.70x collections)
  • Construction progress moved from 90% to 100% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹15 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹26.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA MG Road IFSC Code : SBIN0040006 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata8 km
Kempegowda Int'l Airport14 km
MG Road / city centre16 km
Bellandur–Marathahalli belt22 km
Whitefield IT hub22 km
Electronic City31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Constructions.
Constructions has 20 projects registered in Bangalore, 5 completed, 1 past RERA deadline.
2 complaints on the K-RERA register against Constructions in Bangalore.

Other projects by this builder in Bangalore

G.r. Samskruthi
Past deadline · 75% built · 52% sold
K&t's SAI Sannidhi
Filing overdue · 100% built · 68% sold
VNR-Gowri Apartment
Filing overdue · 100% built · 0% sold
G V Apartment
On track · 90% built · 0% sold
J V Paradise
On track · 100% built · 100% sold

Other RERA-registered projects in Chikkajala

Major developers building in Chikkajala

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Warrior Central Bay?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026