Mumbai/Project record

MahaRERA · the public record

M R INFRASTRUCTURE AND DEVELOPERS

20TH ROAD, KHAR WEST · M. R. INFRASTRUCTURE & DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2026declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for M R INFRASTRUCTURE AND DEVELOPERS

MahaRERA · P51800024803

Delivery and registration

When is the project declared for completion?

M R INFRASTRUCTURE AND DEVELOPERS is registered with MahaRERA as P51800024803 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

2months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51800024803
Registered on09 Mar 2020
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today2 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for M R INFRASTRUCTURE AND DEVELOPERS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for M R INFRASTRUCTURE AND DEVELOPERS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
KHAR SHAKTI - TENANTS WING - A WING1G+15-
PALI CARTERS - SALE WING- B WING1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026We would like to request your good self and to kindly grant for Rera Extension for completion of project up to 31-12-2026. There was delay in completion of project due to various

Location, Land & Connectivity

Located at 20TH ROAD, KHAR WEST, PLOT NO 676 TO 679, CTS E/86-16, Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by KHAR SAMATA CHS, to the east by D P ROAD and to the west by KHAR SHALIMAR CHS. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khar West

Searock Residences
declared completion Oct 2026 · Searock Constructions LLP
259 Park Crest
declared completion Dec 2026 · Shree Krishna Homes PVT LTD
33 West
declared completion Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
declared completion Dec 2026 · Benchmark Projects PVT LTD
Grace Palacio
declared completion Dec 2026 · Grace Infracon & Property Developers
Joy Legend Wing B
declared completion Dec 2026 · Bhavin Jayant Soni
More builders in Khar West

Major developers building in Khar West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

M U Castle
declared completion Dec 2025 · Mohammed Saddique M A Bhati
MAA Elanza
declared completion Dec 2017 · MAA JET Enterprise
MAA Enrich
declared completion Oct 2020 · Dhanish Jitendra Shah
Madhav Baug
declared completion Dec 2029 · Rajyog Projects
Madhav Niwas
declared completion Oct 2021 · Shree Aryadurga Developers Pvt. Ltd.
Madhuban
declared completion Mar 2026 · JE AND VEE Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.