Marvel Gold - Phase II - COLLOSEUM

HARIJAN COLONY VALMIKI NAGAR · Swaroop Constructions Private Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Oct 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Marvel Gold - Phase II - COLLOSEUM

MahaRERA · P51800016143

Delivery and registration

When is the project declared for completion?

Marvel Gold - Phase II - COLLOSEUM is registered with MahaRERA as P51800016143 and the promoter has declared completion for 31 Oct 2024.

31 Oct 2024

declared completion

24months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800016143
Registered on17 Apr 2018
Promoter-declared completion31 Oct 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Marvel Gold - Phase II - COLLOSEUM record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Swaroop Constructions Private Limited is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Marvel Gold - Phase II - COLLOSEUM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
Colloseum1G+2231 Dec 2021

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Marvel Gold - Phase II - COLLOSEUM, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000040823624/11/2023Purushothaman Pillai vs Swaroop Constructions Private Limited and Vasant Developersorder passed
CC00600000040862328/12/2023Swati Avadhoot Tambe vs Jayshil Bhimani, Ketan Bhalodiya, Muljibhai Bhimaniorder passed
CC1240048921/10/2024VISHWAS SAHADEO DALVI vs Swaroop Constructions Private Limitedorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered01 Dec 2023We had received our first CC in April 2019, however due to the pandemic the was stuck for a while, then when the situation got better and things were reopening, we had to face seve
01 Dec 202331 Oct 2024We have completed 80% construction of the building but due to shortage of labour and materials there has been delay in the completion of the construction of the building. We would

Location, Land & Connectivity

Located at HARIJAN COLONY VALMIKI NAGAR, TANK ROAD, CTSO Goregaon, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by CTS 413, to the south by CTS 406, to the east by CTS 554 555 and to the west by CTS 411. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Aureate
declared completion Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
declared completion Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · declared completion Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · declared completion Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing C
Developer in insolvency (NCLT) · declared completion Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing D
Developer in insolvency (NCLT) · declared completion Dec 2026 · Neptune Ventures AND Developers Private
More builders in Bhandup West

Major developers building in Bhandup West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Marvel Pride
declared completion Oct 2027 · Marvellous Builders Private Limited
Mascarenhas Apartment
declared completion Dec 2026 · SAI Universal Realtors & Developers
Mass Ionics
declared completion Jun 2026 · Mass Buildsquare Structure Private Limit
Mass Marquise
declared completion Dec 2029 · Mass Urban Development Corporation
Mass Metropolis
declared completion Sep 2026 · Grace Urban Development Corporation
Mass U-Foria
declared completion Dec 2024 · Grace Mass Housing Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.