Mumbai/Project record

MahaRERA · the public record

MOHINI CASTLE

Khar West · MOHINI SHELTORS PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for MOHINI CASTLE

MahaRERA · P51800005492

Delivery and registration

When is the project declared for completion?

MOHINI CASTLE is registered with MahaRERA as P51800005492 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005492
Registered on11 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Promoter record

What else is this promoter on record for?

MOHINI SHELTORS PRIVATE LIMITED is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MOHINI CASTLE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
MOHINI CASTLE1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 3 “Due for Admission”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Bombay012015Status not supplied
Filed description: Due for Admission
High Court Bombay402015Status not supplied
Filed description: Due for Admission
High Court Bombay3732017Status not supplied
Filed description: Due for Admission

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2022The project has been completed upto 15th floor as per the CC granted by MCGM. The project has been delayed due to the under mentioned reasons which were beyond the control of the

Location, Land & Connectivity

Located at Khar West, Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by existing building, to the south by existing building, to the east by 3rd road and to the west by existing building mohini heights. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district8 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khar West

Searock Residences
declared completion Oct 2026 · Searock Constructions LLP
259 Park Crest
declared completion Dec 2026 · Shree Krishna Homes PVT LTD
33 West
declared completion Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
declared completion Dec 2026 · Benchmark Projects PVT LTD
Grace Palacio
declared completion Dec 2026 · Grace Infracon & Property Developers
Joy Legend Wing B
declared completion Dec 2026 · Bhavin Jayant Soni
More builders in Khar West

Major developers building in Khar West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Mohini Engineers AND Contractors
declared completion Dec 2027 · Haris Gulabrai Chawla
Mohini Tower
declared completion Dec 2019 · Mohini Sheltors Private Limited
Mohite Marvel
declared completion Sep 2026 · Mohite Realtors LLP
Mohite Mrugank
declared completion Sep 2026 · Mohite Infraprojects Private Limited
Monarch Majestic
declared completion Nov 2028 · NEW Monarch Builders AND Contractors
Monarch Prathmesh Chsl
declared completion Mar 2028 · Monarch Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.