NEW THANA CHS

BHASKAR COLONY · GAURANG PROPERTIES PVT. LTD.

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
19 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for NEW THANA CHS

MahaRERA · P51700007377

Delivery and registration

When is the project declared for completion?

NEW THANA CHS is registered with MahaRERA as P51700007377 and the promoter has declared completion for 19 Dec 2021.

19 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700007377
Registered on17 Aug 2017
Promoter-declared completion19 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEW THANA CHS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Deregistered — MahaRERA has deregistered this project — it is off the register.

Promoter record

What else is this promoter on record for?

GAURANG PROPERTIES PVT. LTD. is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEW THANA CHS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
GAURANG HEIGHTS1G+22-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered19 Dec 2020To, The Concerned Officer, Maharashtra Real Estate Regulatory Authority (MahaRERA) Bandra, Mumbai Subject – Self Declaration for extension of due date for the project registere

Location, Land & Connectivity

Located at BHASKAR COLONY, SERVICE ROAD, EASTERN EXPRESS HIGHWAY, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Property of Sahatrabuddhe-Ram Mandir, to the south by Property of Vardhaman Society, to the east by Property of Tirupati Society and to the west by Municipal Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Gaurang Properties Pvt. Ltd. project & its RERA track record →

Other RERA-registered projects in Naupada

Ashirwad Co-Operative Housing Society Ltd
declared completion Oct 2026 · Padmanabh Developers
Platinum Square
declared completion Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
declared completion Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
declared completion Dec 2026 · M/S Pushpak Developers
Adarsha
declared completion Dec 2026 · Adarsha CO Operative Housing Society Lim
Harmony
declared completion Dec 2026 · Trimity Constructions
More builders in Naupada

Major developers building in Naupada

More projects in Thane

Other RERA-registered projects in Thane

New Vaishali CHS Ltd
declared completion Dec 2024 · Joshi & Yash Developers LLP
NEW Vanrai Parag CHS
declared completion Dec 2026 · Vinayak Enterprises
NEW Vidyut Sagar Chsl
declared completion Jun 2024 · SAI Developers
Newa Bhakti Park B Wing
declared completion Dec 2027 · Newa Technocity Private Limited
Newa Business Park II
declared completion Dec 2032 · Newa Reality Infrastructure
Next Crown Landmark
declared completion Dec 2027 · Apex Constructions

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.