MahaRERA Property Intelligence · Near Shangrilla Biscuit Factory · Mumbai Suburban

Primo

P51800001724 · Near Shangrilla Biscuit Factory · promoter Ceear Land Developers

The Drawings Report · ₹4,999

Which home should you ask for in Primo?

We read all 2 approved drawings and 13 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.

Completion date revised 3 times.

  • Which home to ask for — and which to say no to
  • What the drawings put around it
  • What to get in writing before you pay a booking amount

One real find, from a Gurugram colony’s approved papers: 392.997 sq m already used of the 396 allowed — the promised extra room can never be built.

Get it for this project →

Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

Primo is registered with MahaRERA as P51800001724 and the promoter has declared completion for 30 Sep 2026.

30 Sep 2026

declared completion

0months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001724
Registered on29 Jul 2017
Promoter-declared completion30 Sep 2026
Current statusCertificate Signed
Against today0 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Primo record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Primo in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Primo1G+2331 Dec 2020

Legal and disputes

What disputes are disclosed?

38 complaints are on the MahaRERA record for Primo, with orders passed in 37 of them.

38complaints

37with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020990922/02/2022KRUPESH PRAMOD THAKKAR/ KOMAL KRUPESH THAKKAR vs CEEAR LAND DEVELOPERS LLLPorder passed
CC00600000021009118/02/2022Abhishek Walavalkar vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000021008218/02/2022Amey Ram Walavalkar vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000021008818/02/2022DEEPAK POTADAR vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000021009418/02/2022Vivek Kalambe vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000021009218/02/2022Ravindra Pawar vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000021051824/03/2022Minakshi Pappu Yadav vs Ceear Land developers LLPorder passed
CC00600000022087018/04/2022SHIVSHANKAR SAHU vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000022088319/04/2022MAHESHKKUMAR G SAHU vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022088419/04/2022MAHESHKKUMAR G SAHU vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022088920/04/2022GIRISH G GUPTA vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022089320/04/2022KALPESH G KAMBLE vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022090121/04/2022NIKHIL V KANADE vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022090221/04/2022JAYESH KAILASH POTWADE vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000022091021/04/2022MRS LAVANYA LAXMAN DHURI vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000023115312/05/2022MANUBHAI PANCHAL vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000023126623/05/2022VINAY SITARAM GUPTA vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000023126823/05/2022VIKAS SITARAM GUPTA vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000023129425/05/2022JITENDRA GUPTA vs CEAAR LAND DEVELOPERS LLPorder passed
CC00600000026195718/07/2022Merwyn Pawar vs Ceeat Land Developers LLPorder passed
CC00600000029231925/08/2022Umeshchand Shyambihari Pandey vs M/s. Ceear Land Developers LLPorder passed
CC00600000030348929/11/2022SAMEER A SHAIKH vs CEEAR LAND DEVELOPERSorder passed
CC00600000034423714/02/2023Prasad Chandrakant Khadpe vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000034427110/02/2023RAJAN ASWANI vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000035436415/02/2023Nitin Shetty vs Ceear Land Developers LLPorder passed
CC00600000035436615/02/2023SURESH BABURAV AMBOKAR vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000039638422/06/2023RAJU GUPTA vs CEAAR LAND DEVELOPERSorder passed
CC00600000039659411/07/2023MR DAYANAND TUKARAM KADAM vs CEEAR LAND DEVELOPERS LLPorder passed
CC00600000039682502/08/2023Subhan Allah Ikramullah Khan vs Ceear Land Developers LLPorder passed
CC00600000042893924/01/2024Vaibhav Pradeep Palav vs Ceear Land Developersorder passed
CC00600000042903601/02/2024Shankar Nagesh Kadu vs CEEAR Land Developersorder passed
CC00600000042909704/02/2024Sadanand Ganpat Satam vs Ceear Land Developers LLPorder passed
CC00600000042909904/02/2024Alekh Gupta vs Ceear Land Developer LLPorder passed
CC00600000042910104/02/2024Sachin Shridhar Dhumal vs Ceear Land Developers LLPorder passed
CC00600000042942506/03/2024PRIMO ALLOTTEES ASSOCIATION vs Ceear Land Developers LLPorder passed
CC1240009113/09/2024Vivek Basant Kumar Porwal vs Ceear Land Developers LLPorder passed
CC1250378229/10/2025Sheeba David Nadar vs Ceear Land Developers LLPorder passed
CC1260407230/06/2026Biju Francis Koola vs Ceear Land Developers LLPpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022The Promoter was totally in control of the project timelines at the time when initial approvals were obtained until the time the DCPR 2034 was decided to be sanctioned. Lot of time
30 Jun 202231 Mar 2024The RERA certificate of the project has expired on 31.12.2022 and all sales and financial inflows to the project have stopped. Which has reduced the ongoing construction activities
31 Mar 202430 Sep 20261. The Applicant further states that the Applicant couldn’t obtain requisite consent of 51% in spite of all the efforts. The RCC structure is complete till 17th Residential floor/f

Location, Land & Connectivity

Located at Near Shangrilla Biscuit Factory , Off. LBS Road, Mumbai City, Mumbai City, 400078. Per the filed land record, the plot is bounded to the north by S No 201, to the south by G D Marg, to the east by Plot B and to the west by S No 201. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)12 km
Lower Parel / Worli business district21 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

2approved drawings on file
13other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 2 approved sheets are the same drawings the builder filed to get Primo approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing C
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing D
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Primrose
declared completion Jul 2026 · Kaustubh Construction Private Limited
Prinia At L And T Realty Elixir Reserve
possession by Jul 2029 · Larsen & Toubro Ltd.
Prithvi Residency
declared completion Dec 2019 · Prithvi Build Homes
Privilon
possession by Jan 2030 · Bsafal Properties Private Ltd.
Priya CO-Operative Housing Society LTD
declared completion Jun 2026 · Arjunsingh Bhoorsingh Rathore
Priyadarshini Chsl
possession by May 2029 · Pranav Constructions Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026