Gaurav Valley · Thane

The Willows Phase 1

MahaRERA P51700027028 · promoter Origin Realtors Llp

What registered buyers actually paid

₹963 – ₹1,339

per sq ft of carpet, agreement value

Covers 80% of 10 agreements filed with MahaRERA.i

Free example from the dataActual RERA data

Home

7

Carpet area

11,871 sq ft

Typical value

₹1.15 cr

Same stack, floor 205₹1.14–1.59 cr8 registered
See prices for 7 more homesEvery unit and floor, from the filings.Get the Sales Report, ₹2,999 →
On payment30-day refundMahaRERA source
Which home should I ask for?Get the Drawings Report₹4,999 · floor plans, approved drawings and what sits around each home.

Independent analysis · Quietlist · Bengaluru
Paid through Razorpay · WhatsApp +91 86608 81791

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

The Willows Phase 1 is registered with MahaRERA as P51700027028 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700027028
Registered on10 Nov 2020
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Willows Phase 1 record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Origin Realtors Llp is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In The Willows Phase 1, ₹2.99 Cr of a declared ₹21.76 Cr estimated project cost is reported as incurred, about 13.7%, as at the last certified filing with MahaRERA.

13.7%

₹2.99 Cr

of ₹21.76 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In The Willows Phase 1, 10 of 18 homes filed with MahaRERA are recorded as sold or booked (6 with registered agreements and 4 booked), about 56%, and 8 remain available.

56%sold

10 of 18 homes

₹13.50 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹7.97 Cr (about 59%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Ground/Floor 01316,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 01416,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 01516,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 01616,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 01716,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 01816,732 sqft (1554.43 sqm)₹2.02 Cr
Ground/Floor 0711,871 sqft (1102.88 sqm)₹1.40 Cr
Ground/Floor 0911,871 sqft (1102.88 sqm)₹1.40 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 09 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 10 homes carry one, and 8 of the 18 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
711,871 sqftRs 1.1500 cr typical, over Rs 1.1429 cr to Rs 1.5900 cr8 filed on this stack, floor 205

A filed consideration is what was registered for one {unit}. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the {unit} is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In The Willows Phase 1, every one of the 8 unsold homes has agreements filed on its own stack. The Sales Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 7 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 18 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
The Willows1G+318-

Unit mix on the filing: 18 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2024The work is only partly left for completion
30 Jun 202431 Dec 20251. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharas
31 Dec 202531 Dec 20271. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous and illegal. Consequently, all projects undertaken by Ravi Development

Location, Land & Connectivity

Located at GAURAV VALLEY, HATKESH ROAD, Borivali, Mumbai Suburban, 401107. Per the filed land record, the plot is bounded to the north by GAURAV TULIP, to the south by S NO 27 10B, to the east by GAURAV ASTER and to the west by GAURAV ORCHID. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park18 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

2approved drawings on file
49other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 2 approved sheets are the same drawings the builder filed to get The Willows Phase 1 approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

THE Woods
declared completion Mar 2022 · Anup Shyam Karnani
The Woods Phase I
declared completion Oct 2020 · Laxmi Buildcon LLP
THE Woods Phase III
declared completion Oct 2021 · Laxmi Buildcon LLP
Tiara
declared completion Mar 2025 · Sagar Enterprise
Tiara Hills Phase I Bldg NO 3, 5 AND 2
possession by Dec 2026 · PNK Space Development PVT LTD
Time Square
possession by Dec 2028 · Phoenix Infrastructure AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026