Pune/Project record

MahaRERA · the public record

Dnyaneshwar Housing Society

Chovisawadi · Dagdu Vithal Mali

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027422

Delivery and registration

When is the project declared for completion?

Dnyaneshwar Housing Society is registered with MahaRERA as P52100027422 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027422
Registered on10 Dec 2020
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dnyaneshwar Housing Society record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dagdu Vithal Mali is the promoter of record on 17 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

17projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Dnyaneshwar Housing Society in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Dnyaneshwar Housing Society1G+630 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Chovisawadi, Near Kids Paradise International School, Khed, Pune, 412105. Per the filed land record, the plot is bounded to the north by Road, to the south by Property of Mr Jadhav and others, to the east by Property of Mr Anant Pandurang Kale and Others and to the west by Dudulgaon Shiv. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Dnyaneshwari Appartment
declared completion Jul 2022 · Nitin Gopal Jagetia
Dnyaneshwari Nisarg Phase 1
possession by Dec 2027 · Dnyaneshwari Developers
Dnyanmanjula
possession by Dec 2026 · Veer Buildcon
Dnyanvishwa
possession by Dec 2030 · Dattakrupa Associates
Doctor House
declared completion Sep 2025 · Kele Realcorp PVT LTD
Dodke Palazzo
declared completion Jun 2026 · Dodke Landmarks

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026