Bangalore/Project record

K-RERA · the public record

PREMIO SIGNATURE

· PREMIO SIGNATURE

Is this the right project?
Which plot should you choose?

Read the free RERA facts below. For help choosing a plot or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
100%construction reportedQ3 2025 filing

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Registered units and project size

Plot Measuring9*Odd
55

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for PREMIO SIGNATURE

K-RERA · PRM/KA/RERA/1268/378/PR/020923/006234

Project facts and comparisons

On the register

Unit mix55 × Plot Measuring9*Odd

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan number32/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date20-05-2023
Project start date26-06-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Plot Measuring9*Odd55100%0 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

25 of 40 compliance document slots are filed as Not Applicable; the remaining 15 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

4 of 4 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

7 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved06-11-2025UGD NOC Final.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved30-05-2023KSPCB NOC.pdf
Engineering Department (PWD) for completion of development worksApproved30-10-2025Engineering NOC Final.pdf
KPTCL- BESCOMApproved30-10-2025CESCOM NOC Final.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSrinivasa Reddy2418852018Mysore, Karnataka - 570011
EngineerUMESH SEBCC/BL/3-6/S-212/89-902018Bengaluru Rural, Karnataka - 560113

Builder track record

RERA filing

Signature Global has 15 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Premio Signature”) (average reported construction progress 51%). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹1.83 Cr collected from buyers, ₹12.16 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹12.16 Cr) exceeded buyer collections (₹1.83 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress100% → 100% (+0 pts)
Buyer collections in available QPRs₹1.83 Cr
Escrow withdrawals in available QPRs₹12.16 Cr (6.66x collections)
  • Across available QPR rows, escrow withdrawals are 6.66x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank Siddartha Nagara IFSC Code : UTIB0003341 Pin Code : 570011. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 122 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City122 km
MG Road / city centre125 km
Bellandur–Marathahalli belt130 km
Outer Ring Road / Manyata131 km
Whitefield IT hub137 km
Kempegowda Int'l Airport150 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Premio Signature. View Premio Signature's full track record →

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.