Bangalore/Project record

K-RERA · the public record

SOWPARNIKA OLIVIA NEST

Anekal · SOWPARNIKA INFRACON

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

99%construction reportedQ1 2026 filing
1units not bookedof 211 · Q1 2026 filing
30 Sep 2027declared completionK-RERA registration · read 21 Sep 2026

The record · free to read

Registration read 21 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Sep 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 21 Sep 2026

Inventory & scale

What this registration contains.

Residential Apartment
211

Filed categories, unchanged · K-RERA registration · read 21 Sep 2026

The whole registration

1.5registered acres

140.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/181022/005334

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2027
Land area6,063 sq m (1.5 acres)
Homes registered211
Tower/wing entries1
Unit mix211 × Residential Apartment

In context

Density140.8 homes per acre
Density in context95th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units211Total inventory registered with K-RERA.
Official carpet area15,127 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area26,978 sqmUseful scale context when comparing density and project cost.
Registered land area6,063 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)218Separate filed counts; these categories may overlap and are not added together.
Covered-parking field204Separate filed counts; these categories may overlap and are not added together.
Open-parking field14Separate filed counts; these categories may overlap and are not added together.
Garage field218Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/498/2018-19Use this to match the sanctioned drawing set shown by the builder.
Plan approval date28-07-2022
Project start date03-10-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential Apartment211100%12,322 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
11121121830 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 211 official flat/unit rows, matching the 211 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK12446.5-69.7 sqm22.0-32.3 sqm124
3 BHK7859.9-79.2 sqm30.3-36.8 sqm78
1 BHK931.0 sqm15.4 sqm9

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
121131.0-79.2 sqm15.4-36.8 sqm211
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G01103 BHK66.7 sqm33.8 sqm1
G02103 BHK66.7 sqm33.8 sqm1
G03103 BHK71.4 sqm35.9 sqm1
G04102 BHK51.0 sqm25.5 sqm1
G05102 BHK49.7 sqm24.9 sqm1
G06102 BHK50.6 sqm24.9 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

17 of 45 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved29-10-2018Sowparnika Olivia Nest NOC Panchayat Water.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved11-03-2019Sowparnika Olivia Nest NOC KSPCB.pdf
KPTCL- BESCOMApproved17-09-2018Revised BescomNOC.pdf
Fire and SafetyApproved17-01-2019Sowparnika Olivia Nest NOC Fire compress.pdf
Airport Authority of IndiaApproved04-09-2018Sowparnika Olivia Nest NOC AAI.pdf
BSNL/Telecommunication DepartmentApproved25-09-2018Sowparnika Olivia Nest NOC BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantMANAS RANJAN KAR0648382014Bengaluru Urban, Karnataka - 560043
EngineerVAIBHAV KUMAR J GBCC/BL-3.6 SE-136/2013/20142013Bengaluru Urban, Karnataka - 560037
ArchitectMANIRAJ DCA/2011/516952011Bengaluru Urban, Karnataka - 560037
ContractorSOWPARNIKA INFRACON PRIVATE LIMITED-2021Bengaluru Urban, Karnataka - 560037

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹2.23 Cr collected from buyers, ₹2.23 Cr withdrawn from the project's escrow account.

Construction progress96% → 99% (+3 pts)
Units sold/booked as registered210/211 (100%)
Buyer collections in available QPRs₹3.07 Cr
Escrow withdrawals in available QPRs₹3.07 Cr (1.00x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 96% to 99% across the filed QPR window.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹18.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Old Airport Road IFSC Code : HDFC0000075 Pin Code : 560017. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub14 km
Bellandur–Marathahalli belt15 km
Electronic City15 km
MG Road / city centre25 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowparnika Infracon.

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sowparnika Olivia Nest?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 21 Sep 2026