Bangalore/Project record

K-RERA · the public record

VIVANSAA AURIGAA

Anekal · VIIJCON PROPERTIES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionK-RERA registration · read 21 Sep 2026
65registered unitsK-RERA registration · read 21 Sep 2026

The record · free to read

Registration read 21 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 21 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 21 Sep 2026

The whole registration

0.7registered acres

86.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/171230/002053

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2018
Land area3,028 sq m (0.7 acres)
Homes registered65
Tower/wing entries2

In context

Density86.9 homes per acre
Density in context66th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units65Total inventory registered with K-RERA.
Registered land area3,028 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)65Separate filed counts; these categories may overlap and are not added together.
Open-parking field24Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date20-04-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A73535-
B63030-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 65 official flat/unit rows, matching the 65 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK5263.4-78.8 sqm0.0 sqm52
NA1378.8-83.6 sqm0.0 sqm13

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A3563.4-83.6 sqm0.0 sqm35
B3063.5-83.6 sqm0.0 sqm30
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-101A12BHK72.6 sqm0.0 sqm1
A-102A12BHK63.4 sqm0.0 sqm1
A-103A12BHK66.8 sqm0.0 sqm1
A-104A1NA78.8 sqm0.0 sqm1
A-105A12BHK70.3 sqm0.0 sqm1
A-201A22BHK77.4 sqm0.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 21 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2018, extended (Extension) to 30 Jun 2024 — both dates have passed with no OC on file. The extension on file was granted on 28 Sep 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/308/PR/220928/002053) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (7 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Sujatha Subramanian vs VIVANSAA AURIGAARefund and delay CompensationAUTHORITY22/07/2025
CHANDRASHEKARA B S vs VIIJCON PROPERTIESNeed justice and Help in closing my loan .AUTHORITY18/10/2023
LAZAR A vs VIVANSAA AURIGAARefund of money and compensationAUTHORITY18/07/2022
Henry Vijay Masih vs VIIJCON PROPERTIESInitiate action against the Respondents, issue directions to Respondent 4 to refrain from recovery proceeding initiated against the Complainants and such other reliefs mentioned in the complaintAUTHORITY15/09/2025
RAJKUMAR SACHHITANAND TARACHAND vs VIIJCON PROPERTIESWould Like RERA to take action to expedite the completion and delivery of the Project as soon as the Pandemic conditions are lifted for construction.AUTHORITY14/02/2025
RAJIV RAI vs VIIJCON PROPERTIESPossession of flat within six months, else refund of the amount paid.AUTHORITY03/02/2025
POOJA PRABHAKAR NAIK vs VIJICON PROPERTIESRefund of Amount paid as per the receipts along with Compensation exactly as per RERA Guidelines.AUTHORITY01/12/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (21 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190319/0002458
19-03-2019
No PossessionVIVANSAA AURIGAADISPOSED AO
CMP/190331/0002518
31-03-2019
Forgery & breach of trust committed by the buildersVIVANSAA AURIGAADISPOSED AO
CMP/190408/0002597
08-04-2019
Delay compensation and few fraud activity identifiedVIVANSAA AURIGAADISPOSED AO
CMP/190420/0002713
20-04-2019
Delivery Data expired , hence need compensation from promoterVIVANSAA AURIGAADISPOSED AO
CMP/190420/0002718
20-04-2019
Pre EMI payment to bank promised by builder is borne by self and excessive delay in project completionVIVANSAA AURIGAAPOSTED FOR ORDERS AUTHORITY FULLBENCH
CMP/190728/0003742
28-07-2019
Promoter Viijcon Properties was suppose to handover my flat 501 Wing A in Vivansaa Auriga latest by December 31st 2018 but its past 7 months still builder is delaying the projectVIVANSAA AURIGAADISPOSED AO
CMP/190924/0004298
24-09-2019
Delay in construction and default of payment of penalty to be paid to the Complainant by the promoter as agreed in the Agreement.VIVANSAA AURIGAADISPOSED AO
CMP/200108/0005170
08-01-2020
Project Delay for 2 years. unable to manage EMI. Need complete refund along with compensationVIVANSAA AURIGAAPOSTED FOR ORDERS AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectForm N Square Architects-2011BTM 2nd Stage, Bangalore
ContractorSan design Consultant Pvt Ltd-20102nd Block Jaya Nagar, Bangalore
Structural engineerManohar Consultants---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹18.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank HSR Layout Branch (IFSC UTIB0000785, a/c …7237). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub9 km
Bellandur–Marathahalli belt10 km
Electronic City13 km
MG Road / city centre20 km
Outer Ring Road / Manyata23 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Viijcon Properties.
27 complaints on the K-RERA register against Viijcon Properties in Bangalore.

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.