Bangalore/Project record

K-RERA · the public record

Feldspar at Brigade El Dorado

Bengaluru North · Brigade Tetrarch

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Dec 2024declared completionK-RERA registration · read 25 Oct 2026
0registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

3 BEDROOM + 2 TOILET
81

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

4.4registered acres

0.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Feldspar at Brigade El Dorado

K-RERA · PRM/KA/RERA/1251/309/PR/210216/003909

Project facts and comparisons

On the register

Declared completion31 December 2024
Land area17,946 sq m (4.4 acres)
Unit mix81 × 3 BEDROOM + 2 TOILET

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Official carpet area60 sqmTotal carpet area reported for the project.
Registered land area17,946 sqmThe land area attached to this K-RERA registration.
Parking total (reconciled)483Separate filed counts; these categories may overlap and are not added together.
Open-parking field118Separate filed counts; these categories may overlap and are not added together.
Garage field483Separate filed counts; these categories may overlap and are not added together.
Project start date27-01-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BEDROOM + 2 TOILET81100%60 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

4 of 33 compliance document slots are filed as Not Applicable; the remaining 29 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2024 — which has passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: BESCOM
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCDocument listed: Fire Force Department
Pollution control (KSPCB)Document listed: KSPCB
Environmental clearanceDocument listed: SEIAA
Airport Authority height clearanceDocument listed: Airport Authority of India

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

1 K-RERA order on this project (PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

Complaints on this project's K-RERA page (6 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/191111/0004685
11-11-2019
Objection to proposed modification of Sanctioned Plan dated 27/03/2019Gallium at Brigade El Dorado (another project by this promoter)DISPOSED AO
CMP/210205/0007582
05-02-2021
Refund of booking amount with interestHelio at Brigade El Dorado (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220209/0008995
09-02-2022
Non Receipt of signed Agreement for SaleGallium at Brigade El Dorado (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/220218/0009030
18-02-2022
Request for refund of flat booking amountHelio at Brigade El Dorado (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220914/0010013
14-09-2022
EOI RefundEmerald & Luminaire Block at Brigade El Dorado (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220915/0010022
15-09-2022
Request for refund of token MoneyKrypton at Brigade Eldorado (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectAbhay Itty Zachariah-1995Off Brunton Road, Richmond Town
Structural engineerN.N.Nagendra Kumar---

Builder track record

RERA filing

Brigade has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Tetrarch”) (average reported construction progress 70%). 30 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: HDFC World Trade Center Bangalore (IFSC HDFC0002710, a/c …1594). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 13 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Kempegowda Int'l Airport7 km
Outer Ring Road / Manyata13 km
MG Road / city centre20 km
Whitefield IT hub21 km
Bellandur–Marathahalli belt23 km
Electronic City33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Brigade Tetrarch. View Brigade Tetrarch's full track record →
Brigade Tetrarch has 10 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Aurum At Brigade El Dorado
Filing overdue · 81% built · 100% sold
Brigade Insignia
Filing overdue · 64% built · 85% sold
Cobalt At Brigade El Dorado
Filing overdue · 61% built · 100% sold
Dioro & Beryl At Brigade El Dorado
Filing overdue · 58% built · 98% sold
Emerald & Luminaire Block At Brigade El Dorado
Filing overdue · 100% built · 99% sold
Gallium At Brigade El Dorado
No filings

Other RERA-registered projects in Gummanahalli

Emerald & Luminaire Block At Brigade El Dorado

Major developers building in Gummanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.