Bangalore/Project record

K-RERA · the public record

SOWPARNIKA THARANGINI PHASE I

Anekal · SOWPARNIKA PROJECTS AND INFRASTRUCTURE

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Dec 2019declared completionK-RERA registration · read 25 Oct 2026
160registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

1 BHK, 2BHK & 3 BHK
160

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

1.7registered acres

96.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for SOWPARNIKA THARANGINI PHASE I

K-RERA · PRM/KA/RERA/1251/308/PR/171015/000200

Project facts and comparisons

On the register

Declared completion31 December 2019
Land area6,724 sq m (1.7 acres)
Homes registered160
Tower/wing entries1
Unit mix160 × 1 BHK, 2BHK & 3 BHK

In context

Density96.3 homes per acre
Density in context76th percentile of 480 Anekal projects (median 75.6)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units160Total inventory registered with K-RERA.
Official carpet area10,142 sqmTotal carpet area reported for the project.
Registered land area6,724 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)160Separate filed counts; these categories may overlap and are not added together.
Open-parking field18Separate filed counts; these categories may overlap and are not added together.
Garage field8Separate filed counts; these categories may overlap and are not added together.
Project start date01-07-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK, 2BHK & 3 BHK160100%10,142 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
THARANGINI3160160-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 160 official flat/unit rows, matching the 160 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK11649.5-55.5 sqm317.4-370.8 sqm116
3BHK4069.3-73.7 sqm456.7-498.8 sqm40
1BHK439.3 sqm247.6 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
THARANGINI16039.3-73.7 sqm247.6-498.8 sqm160
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G01THARANGINI02BHK53.3 sqm347.4 sqm1
G02THARANGINI02BHK53.2 sqm347.4 sqm1
G03THARANGINI02BHK53.2 sqm347.4 sqm1
G04THARANGINI02BHK53.4 sqm347.4 sqm1
G05THARANGINI02BHK53.3 sqm347.4 sqm1
G06THARANGINI02BHK53.2 sqm347.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 19 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2019 — which has passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190324/0002438
24-03-2019
Flat - 122: Parking issue and delay penalty calculationSOWPARNIKA SANVI PHASE II (another project by this promoter)DISPOSED AO
CMP/190625/0003400
25-06-2019
DEFICIENCY OF SERVICE AND UNFAIR TRADE PRACTICESOWPARNIKA PURPLE ROSE (another project by this promoter)DISPOSED AO
CMP/201201/0007151
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/201201/0007152
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/210803/0008202
03-08-2021
Refund of amount against flat cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/220818/0009913
18-08-2022
Sowparnika Ashiyana - Not paying the refundSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220901/0009964
01-09-2022
REFUND OF EXCESS AMOUNT CHARGED & ALLOTMENT OF SUITABLE CAR PARKING ALONG WITH ITS ALLOTMENT LETTERSOWPARNIKA SWASTIKA PHASE II (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220915/0010018
15-09-2022
Compensation for alterations in the original plan without the prior consent of the buyerSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Architect1-11, 1
Contractor1-11, 1

Builder track record

RERA filing

Sowparnika Projects has 13 other K-RERA-registered projects in our records (average reported construction progress 100%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹16.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: HDFC OLD AIRPORT ROAD (IFSC HDFC0000075, a/c …5170). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub10 km
Bellandur–Marathahalli belt12 km
Electronic City14 km
MG Road / city centre22 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowparnika Projects. View Sowparnika Projects's full track record →
Sowparnika Projects has 14 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Sowparnika Projects in Bangalore.

Other projects by this builder in Bangalore

Sowparnika Ashiyana Phase II
Filing overdue · 100% built · 99% sold
Sowparnika Indraprastha
No filings
Sowparnika Purple Rose
No filings
Sowparnika Sanvi Phase II
No filings

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.