Bangalore/Project record

K-RERA · the public record

SRINIVASAM RESIDENCY

· C B DESAI ENGINEERS & BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
76%construction reportedQ1 2026 filing
8units not bookedof 13 · Q1 2026 filing
13registered unitsK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Registered units and project size

2BHK 102,202
2
2BHK 301
1
2BHK 304
1
2BHK 302
1
2BHK 103,203,303
3
2BHK 101,201
2
G-01 Retail Shop
1
2BHK 104,204
2

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.1registered acres

105.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for SRINIVASAM RESIDENCY

K-RERA · PRM/KA/RERA/1259/410/PR/140524/006870

Project facts and comparisons

On the register

Land area499 sq m (0.1 acres)
Homes registered13
Tower/wing entries1
Unit mix2 × 2BHK 102,202, 1 × 2BHK 301, 1 × 2BHK 304, 1 × 2BHK 302, 3 × 2BHK 103,203,303, 2 × 2BHK 101,201, 1 × G-01 Retail Shop, 2 × 2BHK 104,204

In context

Density105.4 homes per acre
Density in context74th percentile of 4913 projects in this register (median 82)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units13Total inventory registered with K-RERA.
Official carpet area1,258 sqmTotal carpet area reported for the project.
Official built-up area1,595 sqmUseful scale context when comparing density and project cost.
Registered land area499 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)15Separate filed counts; these categories may overlap and are not added together.
Covered-parking field15Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberHDMC-23-24/BP/182/1509Use this to match the sanctioned drawing set shown by the builder.
Plan approval date08-09-2023
Project start date15-03-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK 102,202215%81 sqm
2BHK 30118%86 sqm
2BHK 30418%93 sqm
2BHK 30218%90 sqm
2BHK 103,203,303323%69 sqm
2BHK 101,201215%77 sqm
G-01 Retail Shop18%306 sqm
2BHK 104,204215%80 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
SRINIVASAM RESIDENCY4131514.09 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 13 official flat/unit rows, matching the 13 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1268.8-93.1 sqm28.9-38.1 sqm12
SHOP1306.5 sqm108.7 sqm3

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
SRINIVASAM RESIDENCY1368.8-306.5 sqm28.9-108.7 sqm15
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G-01SRINIVASAM RESIDENCY1SHOP306.5 sqm108.7 sqm3
101SRINIVASAM RESIDENCY22 BHK76.9 sqm31.1 sqm1
102SRINIVASAM RESIDENCY22 BHK80.7 sqm31.5 sqm1
103SRINIVASAM RESIDENCY22 BHK68.8 sqm28.9 sqm1
104SRINIVASAM RESIDENCY22 BHK80.1 sqm33.5 sqm1
201SRINIVASAM RESIDENCY32 BHK76.9 sqm31.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

21 of 40 compliance document slots are filed as Not Applicable; the remaining 19 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

0 of 1 applicable approvals are marked Approved in the filing. Other recorded statuses: KPTCL- BESCOM: To Be Applied. Check the linked documents for their scope and validity.

9 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
KPTCL- BESCOMTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRAJEEV R KULKARNI2116162007Dharwad, Karnataka - 580004
EngineerSUSHAMA HIREMATH1284-F1993Dharwad, Karnataka - 580029
ArchitectCHIDAMBER B DESAIHDW/BL/11200/20-212010Dharwad, Karnataka - 580004
ContractorCBDESAI ENGINEERS AND BUILDERS-2016Dharwad, Karnataka - 580002

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.85 Cr collected from buyers, ₹0.85 Cr withdrawn from the project's escrow account.

Construction progress54% → 76% (+22 pts)
Units sold/booked as registered5/13 (38%)
Buyer collections in available QPRs₹1.83 Cr
Escrow withdrawals in available QPRs₹1.87 Cr (1.02x collections)
  • Construction progress moved from 54% to 76% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 1.02x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹26.2 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Karnataka Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 388 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Kempegowda Int'l Airport384 km
Outer Ring Road / Manyata388 km
MG Road / city centre393 km
Bellandur–Marathahalli belt402 km
Whitefield IT hub404 km
Electronic City407 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Desai Engineers.

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.