Developer RERA record

Casagrand

Casagrand has 21 RERA-registered projects: 8 projects under construction, Bengaluru averaging 41% construction; 11 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

Flagged
Delivery signal
8
Under construction
11
Past declared date
83%
Bengaluru inventory booked
141
RERA complaints filed

Under construction

Under construction — 8 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

Bengaluru: 1.4/5 ★☆☆☆☆ (151 MouthShut reviews)

ProjectCityProgress / possession
CASAGRAND HAZENBengaluru73%
CASAGRAND FLAMINGOBengaluru62%
Casagrand KeatswayBengaluru60%
CASAGRAND AMORBengaluru35%
CASAGRAND CASABLANCABengaluru26%
CASAGRAND REGALBengaluru13%
CASAGRAND PROMENADEBengaluru7%
CASAGRAND ESTANCIABengaluru3%
Considering a specific Casagrand project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (11)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Casa Grande LuxusBengaluru2018-04
Casa Grande NeonaBengaluru2019-06
Casagrand RoyceBengaluru2019-12
Casa Grande LorenzaBengaluru2020-10
Casagrand FlorellaBengaluru2022-03
Casagrand Florella Phase 2Bengaluru2022-08
Casagrand OrlenaBengaluru2024-08
CASAGRAND GALILEOBengaluru2025-02
CASAGRAND AQUENEBengaluru2025-06
Casagrand Meridian (70.0% built)Bengaluru2025-11
CASAGRAND ZAIDEN (60.0% built)Bengaluru2026-03
Registered, no progress filed yet (2)click to expand
ProjectCity
CASAGRAND VIVACITYBengaluru
CASAGRAND MOONDANCEBengaluru

RERA complaints & orders

Regulatory record

141 total complaints filed — among the highest complaint volumes of any builder we track (#3 of 63).

140
Karnataka RERA complaints
1
MahaRERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Casagrand's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.