ANAND MANGAL

Mumbai Suburban · SAMARTH KRUPA DEVELOPER

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Oct 2020declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for ANAND MANGAL

MahaRERA · P51800008706

Delivery and registration

When is the project declared for completion?

ANAND MANGAL is registered with MahaRERA as P51800008706 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800008706
Registered on19 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANAND MANGAL record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANAND MANGAL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
ANAND MANGAL1G+7-

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for ANAND MANGAL, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002291815/01/2018YOBU JOSEPH vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002293116/01/2018RAGHUNATH SAWANT vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002296017/01/2018PRASAD DAGLE vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002298918/01/2018KASHINATH SHIRWADKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000005641802/10/2018KASHINATH SHIRWADKAR vs M/s Samarth Krupa Developerorder passed
CC00600000002300819/01/2018GOPAL KAWALI vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000005762910/01/2019GOPAL KAWALI vs SAMARTH KURPA DEVELOPERorder passed
CC00600000007941622/05/2019ANAND MANGAL ASSOCIATION OF ALLOTTEES vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000035451425/02/2023Gopal Narsappa Kawali vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002301620/01/2018DINESH BHALEKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002303421/01/2018SHIVAJYOTHI YOBU vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002314230/01/2018PRASHANT MUNGEKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC1250153408/05/2025Dinesh Sakharam Bhalekar and Diksha Dinesh Bhalekar vs SAMARTH KRUPA DEVELOPERorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Because of our site condition we could not get drainage connection now we have got the permission and completed the drainage work and applying for OC.
30 Apr 202030 Apr 2020Required extension to obtain the required Occupation Certificate for the project.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by DP ROAD, to the south by NES SCHOOL, to the east by CTS NO 464 AND CTS NO 468 and to the west by NES SCHOOL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Tirupati Apartments Chsl
declared completion Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
declared completion Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
declared completion Dec 2026 · Lohitka Properties LLP
Atmosphere O2
declared completion Dec 2026 · Atmosphere Realty Pvt Ltd
Rejuve 360 - Tower A
declared completion Dec 2026 · Elevated Avenue Realty LLP
Transcon Fortune 500 Tower 1
declared completion Dec 2026 · Samta Builders Pvt. Ltd.
More builders in Mulund West

Major developers building in Mulund West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Anand Milan Co.op. Housing Society Limited
declared completion Mar 2024 · Anand Milan Co.op. Housing Society Limit
Anand ONE
declared completion Dec 2030 · Mahalakshmi Padam Private Limited
Anand Tower
declared completion Oct 2020 · Arihant Associates
Anand Villa
declared completion Dec 2027 · Ivaan Buildcon LLP
Ananda CHS Wing B
declared completion Mar 2027 · Ananda Living Spaces LLP
Anandam
declared completion Aug 2026 · M/s Analiza Realty Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.