GALAXY TECH PARK

SURAI NAKA · GURUCHARANSINGH SURENDRASINGH SAMLOK

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

418units filed as unsoldInventory · 18 October 2026
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for GALAXY TECH PARK

MahaRERA · P51700015509

Delivery and registration

When is the project declared for completion?

GALAXY TECH PARK is registered with MahaRERA as P51700015509 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700015509
Registered on07 Mar 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GALAXY TECH PARK record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

What the filings record, unit by unit

Read from MahaRERA on 18 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 40 units carry one, and 418 of the 463 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
C-102360 sqftRs 24.00 lakh typical, over Rs 8.65 lakh to Rs 40.00 lakh
7 unusually low or high filed amounts are included in this range. Check the individual entries before using it to discuss a price.
11 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In GALAXY TECH PARK, 323 of the 418 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 417 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
A1G+331 Dec 2017
B1G+331 Dec 2020
C1G+331 Dec 2020
D1G+331 Dec 2020
E1G+331 Dec 2020
F1G+331 Dec 2020

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for GALAXY TECH PARK, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039735002/09/2023JAYPRAKASH SUKHDEV VISHWAKARMA vs GURUCHARANSINGH SAMLOKorder passed
CC00600000033383229/12/2022Appasaheb Subhash Jadhav vs Gurucharansingh Surendrasingh Samlokorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022I/We the Promoters of the Project name Galaxy Tech Park registered under project registration no P51700015509. We are thankful to the MahaRERA Authority for granting a six months e
30 Dec 202231 Dec 2025Respected Sir, This is to bring to your notice that this project is delayed due to the various reasons lack of material issue, covid 19 ,shortage of labour and we have some unso

Location, Land & Connectivity

Located at SURAI NAKA, ANJUR, Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by 303, to the south by 305, to the east by 301 and to the west by 302. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 18 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ21 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district33 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Upper Thane - Woodlands A, B AND J
declared completion Oct 2026 · Lodha Developers Limited
Multani Residency
declared completion Nov 2026 · M R Developers
Omkar Residency A-Wing
declared completion Dec 2026 · K K Group
Arunoday Heights
declared completion Dec 2026 · Sankalp Builders And Developers
Atlanta Edenworld Phase III
Not filing quarterly progress reports · declared completion Dec 2026 · SAI Balaji Developer
Narayani Dham Building NO 2A AND 2B
declared completion Dec 2026 · Maya Developer
More builders in Bhiwandi

Major developers building in Bhiwandi

More projects in Thane

Other RERA-registered projects in Thane

Galaxy Tower
declared completion Dec 2026 · Eamkay Enterprises
Galaxy Wing 5
declared completion Dec 2025 · Bright SKY Heights Builders AND Develope
Gami Asters A Wing
declared completion Dec 2026 · Thalia AND Gami Enterprises
Gami Asters B Wing
declared completion Dec 2026 · Thalia AND Gami Enterprises
Gami Avant
declared completion Dec 2029 · LAL Gebi Infra Private Limited
Gami Ayur
declared completion Dec 2030 · Narayani Trexim Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.