LILAVATI RESIDENCY

KAMATGHAR · M M DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for LILAVATI RESIDENCY

MahaRERA · P51700030892

Delivery and registration

When is the project declared for completion?

LILAVATI RESIDENCY is registered with MahaRERA as P51700030892 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51700030892
Registered on20 Sep 2021
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LILAVATI RESIDENCY record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

M M DEVELOPERS is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LILAVATI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
BUILDING NO A1G+7-
BUILDING NO B1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2025Project delay is due to we have applied for new permission and the said extention will also be competed in the said time till 30/12/2025.

Location, Land & Connectivity

Located at KAMATGHAR, KAMATGHAR, Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by S NO 116, to the south by S NO 112, to the east by S NO 121 HISSA NO 5 and to the west by S NO 121 HISSA NO 3. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Upper Thane - Woodlands A, B AND J
declared completion Oct 2026 · Lodha Developers Limited
Multani Residency
declared completion Nov 2026 · M R Developers
Omkar Residency A-Wing
declared completion Dec 2026 · K K Group
Arunoday Heights
declared completion Dec 2026 · Sankalp Builders And Developers
Atlanta Edenworld Phase III
Not filing quarterly progress reports · declared completion Dec 2026 · SAI Balaji Developer
Narayani Dham Building NO 2A AND 2B
declared completion Dec 2026 · Maya Developer
More builders in Bhiwandi

Major developers building in Bhiwandi

More projects in Thane

Other RERA-registered projects in Thane

Lily A And B
declared completion Sep 2030 · Lodha Developers Limited
Lily C And D
declared completion Sep 2030 · Lodha Developers Limited
Lily E And F
declared completion Sep 2034 · Lodha Developers Limited
Lily G And H
declared completion Sep 2030 · Lodha Developers Limited
Lily I And J
declared completion Sep 2030 · Lodha Developers Limited
Lily K And L
declared completion Sep 2035 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.