Mumbai/Project record

MahaRERA · the public record

PUSHPAK HEIGHTS

malad · PUSHPAK REALTIES PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PUSHPAK HEIGHTS

MahaRERA · P51800007692

Delivery and registration

When is the project declared for completion?

PUSHPAK HEIGHTS is registered with MahaRERA as P51800007692 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800007692
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PUSHPAK HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PUSHPAK HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
PUSHPAK HEIGHTS1G+23-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PUSHPAK HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005789211/09/2019PULIN NAVINCHANDRA KUSUMGAR vs Jignesh Shahorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Project was nearing completion but due to discrepancy in calculations of land rate as raised by revenue and planning authorities, work had came to standstill. As the Plot is reflec
30 Dec 202030 Jun 2022Due to “SECOND WAVE” which crested in the state of Maharashtra forcing the state government to once again impose fresh restrictions and labour exodus in the country to their native

Location, Land & Connectivity

Located at malad, daftary road, Andheri, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by ROAD, to the south by SOUTH VILLAGE BOUNDARY, to the east by ROAD and to the west by CTS NO 534 535 536 537. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Bhagat Grandeur
declared completion Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
declared completion Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
declared completion Dec 2026 · Jinam Realtors
Runwal Nexus
declared completion Dec 2026 · Asmira Ventures Private Limited
Adhrit
declared completion Dec 2026 · Mundara Developers
Ajmera Boulevard
declared completion Dec 2026 · Ajmera Boulevard Private Limited
More builders in Malad West

Major developers building in Malad West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Pushpanjali Residency
declared completion Dec 2025 · Shree Dham Developers
Qadri Manzil
declared completion Dec 2029 · Qadri Constructions
Quality Victoria
declared completion Dec 2023 · Quality Construction Developers
Queen Of Spaces
declared completion Jun 2027 · Space India Builders And Developers LLP
Queens Avenue
declared completion Dec 2027 · V Laxmi Estate Developers Private Limite
Queens Glory
declared completion Dec 2027 · Vaibhavlaxmi Builders & Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.