Mumbai/Project record

MahaRERA · the public record

RAJ ALTEZZA

MULUND WEST · RAJGURU DEVELOPERS PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jul 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RAJ ALTEZZA

MahaRERA · P51800007125

Delivery and registration

When is the project declared for completion?

RAJ ALTEZZA is registered with MahaRERA as P51800007125 and the promoter has declared completion for 31 Jul 2024.

31 Jul 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800007125
Registered on17 Aug 2017
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJ ALTEZZA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJ ALTEZZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+32.

BuildingWingsFloorsDeclared completion
RAJ ALTEZZA1G+3231 Dec 2019

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for RAJ ALTEZZA, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017184713/01/2020BHAKTI SAWANT vs PRATIK PATELorder passed
CC00600000019369410/08/2020Pratibha Bahulkar vs Rajguru Developers Private Limitedorder passed
CC00600000019685610/05/2021Budhia Sutari Patta vs Rajguru Developers Pvt. Ltdorder passed
CC00600000019834921/09/2021Roshan Sylvester Castelino vs Rajguru Developers Pvt Ltdorder passed
CC00600000019629719/03/2021RAHUL VISANJI VISARIYA vs PRATIK HARISH PATELorder passed
CC00600000019581004/02/2021Om Shanti Ambika Welfare Association vs Rajguru Developers Private Limitedorder passed
CC00600000019652027/03/2021Veeren Velji Shah vs Rajguru Developers Private Limitedorder passed
CC00600000019703725/05/2021Reena Bipin Apandkar vs Rajguru Developers Pvt Ltdorder passed
CC00600000019747926/07/2021VIJAY LAXMINARAYAN KUSHWAHA vs RAJGURU DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019782731/07/2021Manisha Rakesh Rathod vs Rajguru developers private limitedorder passed
CC00600000019798215/08/2021Suresh Jha vs Rajguru Developers Pvt. Ltd.order passed
CC00600000028211727/07/2022Dhansukh Akhai Patel vs Rajguru Developers Private Limitedorder passed
CC00600000042961014/03/2024MAHESH JETHALAL JOSHI vs PRATIK PATELorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 20201. Majority of our customers were seeking 98% Home Loan Finance. Loans were sanctioned & / or under process for sanction majorly by NBFC’s i.e. Indiabulls, DHFL etc. Since Sept-201
30 Dec 202031 Jul 20241) In view of COVID-19 pandemic and consequent nation-wide lockdown with effect from March, 2020, reverse migration of labourers to their native places and caused break in supply c

Location, Land & Connectivity

Located at MULUND WEST, J N ROAD, Mumbai City, Mumbai City, 400080. Per the filed land record, the plot is bounded to the north by CTS 1462 AND 1463, to the south by REHAB BUILDING, to the east by CENTRAL RAILWAY and to the west by NALLA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Tirupati Apartments Chsl
declared completion Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
declared completion Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
declared completion Dec 2026 · Lohitka Properties LLP
Atmosphere O2
declared completion Dec 2026 · Atmosphere Realty Pvt Ltd
Rejuve 360 - Tower A
declared completion Dec 2026 · Elevated Avenue Realty LLP
Transcon Fortune 500 Tower 1
declared completion Dec 2026 · Samta Builders Pvt. Ltd.
More builders in Mulund West

Major developers building in Mulund West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

RAJ Capital
declared completion Aug 2026 · RAJ Insignia Private Limited
RAJ Ekjyot Sukruti
declared completion Dec 2018 · Sadguna Realty
RAJ ONE
declared completion Aug 2027 · RAJ Realtors
RAJ Pantheon
declared completion Dec 2025 · Not Available
Raj Residency
declared completion Dec 2022 · Not Available
Raj Shivganga
declared completion Dec 2019 · Raj Arcades & Enclaves Private Limit

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.