BELLA CASA

KHARADI · VIJAY BALASAHEB PATHARE

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for BELLA CASA

MahaRERA · P52100025790

Delivery and registration

When is the project declared for completion?

BELLA CASA is registered with MahaRERA as P52100025790 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100025790
Registered on16 Jul 2020
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BELLA CASA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BELLA CASA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
BELLA CASA1G+731 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2023Projected is delayed due to Covid 19 and heavy rain during FY 2020-21 & FY 2021-22, Your office has asked for 1. Form 5 auditor report 2. Form D Declaration 3. Declaration of Sold
31 Mar 202330 Sep 2023100% Civil Work is completed and site development is in process. We are in process to obtaining all NOC from various department regarding completion of project but it will take few

Location, Land & Connectivity

Located at KHARADI, SR NO 63, RAJARAM PATIL NAGAR, Haveli, Pune, 411014. Per the filed land record, the plot is bounded to the north by REMAINING PART OF SR NO 63, to the south by REMAINING PART OF SR NO 63, to the east by PROPOSE 6 MTR ROAD and to the west by REMAINING PART OF SR NO 63. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Ganga Platinum A
declared completion Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
declared completion Dec 2026 · Prime Estate
Grant Bay
declared completion Dec 2026 · Gagan Landmarks LLP
Bramhacorp Smart
declared completion Dec 2026 · Bramhacorp Limited
Orville Business Port
declared completion Dec 2026 · Siddhesh Properties
Panchshil Avenue
declared completion Dec 2026 · New Level Business LLP
More builders in Kharadi

Major developers building in Kharadi

More projects in Pune

Other RERA-registered projects in Pune

Bella Casa - Phase 1
declared completion Dec 2026 · Kakkad Infra LLP
Bella Casa Royale Tower/type O
declared completion Jun 2029 · Rachana Developer
Bellacasa Royale Tower B/ Type B
declared completion Dec 2026 · Rachana Lifespaces
Bellacasa Royale Tower N1
declared completion Dec 2027 · Rachana Life Spaces
Bellacasa Royale Tower N2
declared completion Dec 2027 · Rachana Developer
Bellacasa Royale Tower / Type A
declared completion Jun 2027 · Rachana Lifespaces

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.