MahaRERA Property Intelligence · Village Tathawade Pune · Pune

KOHINOOR SAPPHIRE II

P52100026685 · VILLAGE TATHAWADE PUNE · promoter Rising Associates

The Drawings Report · ₹4,999

Which home should you ask for in KOHINOOR SAPPHIRE II?

We read all 6 approved drawings and 12 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.

  • Which home to ask for — and which to say no to
  • What the drawings put around it
  • What to get in writing before you pay a booking amount

One real find, from a Gurugram colony’s approved papers: 392.997 sq m already used of the 396 allowed — the promised extra room can never be built.

Get it for this project →

Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

KOHINOOR SAPPHIRE II is registered with MahaRERA as P52100026685 and the promoter has declared completion for 30 Sep 2024.

30 Sep 2024

declared completion

24months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026685
Registered on21 Oct 2020
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KOHINOOR SAPPHIRE II record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Rising Associates is the promoter of record on 42 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

42projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KOHINOOR SAPPHIRE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A1G+11-
B1G+11-
C1G+13-
D1G+13-
E1G+13-
F1G+13-
G1G+13-
H1G+13-
I1G+13-
MAHDA1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILLAGE TATHAWADE PUNE, SURVEY NO 9/2B AND SURVEY NO 10/1 , Pune City, Pune, 411033. Per the filed land record, the plot is bounded to the north by BY RIVER, to the south by BY D P ROAD, to the east by S NO 11 13 AND 14 and to the west by S NO 10 PART AND 9 PART. These are the boundaries as recorded in the filed land record.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

6approved drawings on file
12other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 6 approved sheets are the same drawings the builder filed to get KOHINOOR SAPPHIRE II approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rising Associates is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Rising Associates project & its RERA track record →

Other flagged projects by Rising Associates

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Kohinoor Sapphire III
declared completion Feb 2026 · Rising Associates
Kohinoor Satori Mahalunge
possession by Dec 2029 · Intofinity Promoters Private Limited
Kohinoor Shangrila Phase 2
declared completion Dec 2025 · Kohinoor Properties
Kohinoor Uptown Avenue
possession by Dec 2029 · Moonstone Realinfra Private Limited
Kohinoor Viva Pixel- Phase I
declared completion Jun 2026 · Rising Associates
Kohinoor Viva Pixel- Phase II
possession by Jun 2028 · Rising Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026