Bangalore/Project record

K-RERA · the public record

JWALAMALA TEMPLE CREST

Bengaluru South · Mehta Real Assets Bangalore

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
100%construction reportedQ4 2025 filing
32units not bookedof 36 · Q4 2025 filing
23 Oct 2026declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

23 Oct 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

2BHK & 3BHK FLATS
36

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

0.6registered acres

59.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for JWALAMALA TEMPLE CREST

K-RERA · PRM/KA/RERA/1251/310/PR/270625/007874

Project facts and comparisons

On the register

Declared completion23 October 2026
Land area2,448 sq m (0.6 acres)
Homes registered36
Tower/wing entries1
Unit mix36 × 2BHK & 3BHK FLATS

In context

Density59.5 homes per acre
Density in context25th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units36Total inventory registered with K-RERA.
Official carpet area3,658 sqmTotal carpet area reported for the project.
Official built-up area3,594 sqmUseful scale context when comparing density and project cost.
Registered land area2,448 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)49Separate filed counts; these categories may overlap and are not added together.
Covered-parking field45Separate filed counts; these categories may overlap and are not added together.
Open-parking field5Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Ad.com./BMH/1971/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date27-09-2023
Project start date01-11-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK & 3BHK FLATS36100%3,658 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
JWALAMALA TEMPLE CREST4364914.84 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 36 official flat/unit rows, matching the 36 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1988.0-96.0 sqm52.0-56.0 sqm19
3 BHK17116.0-136.0 sqm68.0-79.0 sqm17

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
JWALAMALA TEMPLE CREST3688.0-136.0 sqm52.0-79.0 sqm36
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
GF-001JWALAMALA TEMPLE CREST13 BHK135.0 sqm79.0 sqm1
GF-005JWALAMALA TEMPLE CREST13 BHK133.0 sqm77.0 sqm1
GF-006JWALAMALA TEMPLE CREST12 BHK93.0 sqm54.0 sqm1
GF-008JWALAMALA TEMPLE CREST13 BHK129.0 sqm75.0 sqm1
GF-009JWALAMALA TEMPLE CREST13 BHK116.0 sqm68.0 sqm1
GF-010JWALAMALA TEMPLE CREST13 BHK118.0 sqm69.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

17 of 34 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 23 Oct 2026 — which has passed with no OC on file.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

0 of 2 applicable approvals are marked Approved in the filing. Other recorded statuses: Water supply and sewage board: Applied; KPTCL- BESCOM: Applied. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApplied24-04-2024View NOC
KPTCL- BESCOMApplied27-10-2023View NOC

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantVinay G Lal2191332019Bengaluru Rural, Karnataka - 560006
EngineerMANJUNATH G S123-7892005Bengaluru Rural, Karnataka - 560004
ArchitectSATHASHIVAM VBCC/BL-3.6/A-2868/2017-182018Bengaluru Rural, Karnataka - 560004
ContractorVENKATRAYAPPA-2025Bengaluru Rural, Karnataka - 560004

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹1.36 Cr collected from buyers, ₹0.44 Cr withdrawn from the project's escrow account.

Construction progress95% → 100% (+5 pts)
Units sold/booked as registered4/36 (11%)
Buyer collections in available QPRs₹1.36 Cr
Escrow withdrawals in available QPRs₹0.44 Cr (0.32x collections)
  • Construction progress moved from 95% to 100% across the filed QPR window.
  • The builder has drawn 0.32x of buyer collections from escrow (about 32% of the ₹1 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹72.2 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: ICICI Bank Basavanagudi IFSC Code : ICIC000317 Pin Code : 560004. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City8 km
Bellandur–Marathahalli belt8 km
MG Road / city centre8 km
Whitefield IT hub16 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mehta Real.

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.