Bangalore/Project record

K-RERA · the public record

PURSUIT OF HAPPINESS

Bengaluru South · MUPPIRI DEVELOPERS

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
01 Dec 2024declared completionK-RERA registration · read 25 Oct 2026
147registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

FLATS
147

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

1.4registered acres

107.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for PURSUIT OF HAPPINESS

K-RERA · PRM/KA/RERA/1251/310/PR/200103/003131

Project facts and comparisons

On the register

Declared completion1 December 2024
Land area5,548 sq m (1.4 acres)
Homes registered147
Tower/wing entries1
Unit mix147 × FLATS

In context

Density107.2 homes per acre
Density in context86th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units147Total inventory registered with K-RERA.
Official carpet area11,693 sqmTotal carpet area reported for the project.
Registered land area5,548 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)165Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-12-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
FLATS147100%11,693 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
PURSUIT OF HAPPINESS6147165-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 147 official flat/unit rows, matching the 147 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK9195.4-104.3 sqm40.5-44.3 sqm91
2BHK5671.2-87.3 sqm30.2-37.1 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
PURSUIT OF HAPPINESS14771.2-104.3 sqm30.2-44.3 sqm147
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101PURSUIT OF HAPPINESS02BHK76.0 sqm32.2 sqm1
102PURSUIT OF HAPPINESS03BHK99.9 sqm42.4 sqm1
103PURSUIT OF HAPPINESS03BHK97.4 sqm41.3 sqm1
104PURSUIT OF HAPPINESS03BHK95.4 sqm40.5 sqm1
105PURSUIT OF HAPPINESS03BHK97.4 sqm41.3 sqm1
106PURSUIT OF HAPPINESS03BHK95.4 sqm40.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

2 of 22 compliance document slots are filed as Not Applicable; the remaining 20 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 01 Dec 2024, extended (Covid Extension) to 01 Sep 2025 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: BESCOM
Water & sewage (BWSSB/KWSSB)Document listed: BWSSB
Fire NOCDocument listed: Fire Force Department
Pollution control (KSPCB)Document listed: KSPCB
Environmental clearanceDocument listed: SEIAA
Airport Authority height clearanceDocument listed: Airport Authority of India

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectT P SREE LAKSHMI-2008jayanagar, bangalore
ContractorRAVI J-2012BSK 3rd Stage, bangalore
Structural engineerA RAMCHANDRAN---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹27.2 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Karnataka Bank Ltd. BASAVANAGUDI (IFSC KARB0000090, a/c …6101). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City10 km
MG Road / city centre12 km
Bellandur–Marathahalli belt14 km
Outer Ring Road / Manyata19 km
Whitefield IT hub22 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Muppiri Developers.

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.