Mumbai/Project record

MahaRERA · the public record

PENTAGON HEIGHTS

Bhiwandi · DAMJI HARI CONSTRUCTIONS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
29 Nov 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PENTAGON HEIGHTS

MahaRERA · P51700010871

Delivery and registration

When is the project declared for completion?

PENTAGON HEIGHTS is registered with MahaRERA as P51700010871 and the promoter has declared completion for 29 Nov 2019.

29 Nov 2019

declared completion

83months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700010871
Registered on31 Aug 2017
Promoter-declared completion29 Nov 2019
Current statusCertificate Signed
Against todayabout 83 months past the declared date

Promoter record

What else is this promoter on record for?

DAMJI HARI CONSTRUCTIONS is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PENTAGON HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
PENTA 1 - BUILDING A1G+812 Oct 2017
PENTA 3 - BUILDING B1G+1528 Mar 2019

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for PENTAGON HEIGHTS, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001219425/12/2017Zaheed Shamsuddin Shaikh & 3 Others vs Paresh Bhanushali & Other Promotersorder passed
CC00600000002330512/09/2018ansari sharif saleem vs DAMJI HARI CONSTRACTIONorder passed
CC00600000002316331/01/2018Afroze Amanulla Khalipha vs DAMJI HARI CONSTRUCTIONSorder passed
CC00600000004449112/05/2018DAMJI HARI CONSTRUCTIONS vs Mohammed Shafiq Ayub Ansariorder passed
CC00600000005621315/09/2018Abdul Hamid Abdul Latif Shaikh vs M/S DAMJI HARI CONSTRUCTIONorder passed
CC00600000019869316/10/2021VASI AHMAD MOMIN AND NUSRAT JAHAN VASI AHMAD MOMIN vs M/S. DAMJI HARI CONSTRUCTIONSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Nov 2019WE HAD APPLIED FOR OCCUPATION CERTIFICATE FOR BUILDING B (PENTA-3) DATED 15.11.2018. WE ARE EXPECTING THE SAME APPROVAL BEFORE OUR PROPOSED EXTENDED DATE OF COMPLETION. WE HAD REC

Location, Land & Connectivity

Located at Bhiwandi, Andheri, Mumbai Suburban, 421302. Per the filed land record, the plot is bounded to the north by ADJOINING SURVEY NO 92, to the south by ADJOINING SURVEY NO 72-4, to the east by ADJOINING SURVEY NO 72-3 AND 72-4 and to the west by ADJOINING SURVEY NO 95. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 28 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ29 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Upper Thane - Woodlands A, B AND J
declared completion Oct 2026 · Lodha Developers Limited
Multani Residency
declared completion Nov 2026 · M R Developers
Omkar Residency A-Wing
declared completion Dec 2026 · K K Group
Arunoday Heights
declared completion Dec 2026 · Sankalp Builders And Developers
Atlanta Edenworld Phase III
Not filing quarterly progress reports · declared completion Dec 2026 · SAI Balaji Developer
Narayani Dham Building NO 2A AND 2B
declared completion Dec 2026 · Maya Developer
More builders in Bhiwandi

Major developers building in Bhiwandi

More projects in Thane

Other RERA-registered projects in Thane

Pentagon Heights
declared completion Dec 2032 · Damji Hari Constructions
PG Swara
declared completion Dec 2028 · Yogesh Shankar Pawar
PG Vatika
declared completion Dec 2026 · Gurukrupa Enterprises
PG Vatika Wing E AND F
declared completion Dec 2030 · Gurukrupa Enterprises
PG Vrundavan
declared completion Dec 2027 · Maruti Corporation
Phatak Wada
declared completion Jun 2025 · Aditya Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.