Polaris B 20-21

MULUND WEST · Nirmal Lifestyle Ltd

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Polaris B 20-21

MahaRERA · P51800006844

Delivery and registration

When is the project declared for completion?

Polaris B 20-21 is registered with MahaRERA as P51800006844 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800006844
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Polaris B 20-21 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Nirmal Lifestyle Ltd is the promoter of record on 7 projects registered with MahaRERA.

7projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Polaris B 20-21 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Polaris B 20-21 flrs1G+1-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Polaris B 20-21, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000066418/09/2017Mehul Raghani vs Rajeev Jainorder passed
CC00600000004445504/06/2018PRAVIN PANDURANG LOKE AND PRACHI PRAVIN LOKE vs NIRMAL LIFESTYLE LIMITED AND ITS DIRECTORSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020WIP
30 Dec 202030 Dec 2020AS PER ATTACHED APPLICATION / DOC

Location, Land & Connectivity

Located at MULUND WEST, LBS MARG, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by Deep Mandir Theatre, to the south by Layout RG, to the east by Proposed Building and to the west by Wing A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Tirupati Apartments Chsl
declared completion Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
declared completion Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
declared completion Dec 2026 · Lohitka Properties LLP
Atmosphere O2
declared completion Dec 2026 · Atmosphere Realty Pvt Ltd
Rejuve 360 - Tower A
declared completion Dec 2026 · Elevated Avenue Realty LLP
Transcon Fortune 500 Tower 1
declared completion Dec 2026 · Samta Builders Pvt. Ltd.
More builders in Mulund West

Major developers building in Mulund West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Polo Matrix
declared completion Dec 2026 · Polo Infra Developers Private Limited
Polys Cooperative Housing Society
declared completion Jul 2018 · Parsh Housing PVT LTD
Pooja CO-Operative Housing Society Limited
declared completion Oct 2029 · Arhat Arham Lifespace Realtors Private L
Poonam Celeste
declared completion Aug 2026 · PL7 Realty Pvt. Ltd.
Poonam Chsl
declared completion Oct 2027 · Digam Lifespaces LLP
Poonam Enclave
declared completion Jan 2020 · Prakash Raghavji Patel

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.