Definer Upper Deck

Bengaluru East · Definer Ventures

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
100%construction reportedQ3 2025 filing
32units not bookedof 110 · Q3 2025 filing
31 Dec 2025declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

2BHK
110

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

1.5registered acres

73.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Definer Upper Deck

K-RERA · PRM/KA/RERA/1251/446/PR/230123/005646

Project facts and comparisons

On the register

Declared completion31 December 2025
Land area6,070 sq m (1.5 acres)
Homes registered110
Tower/wing entries1
Unit mix110 × 2BHK

In context

Density73.3 homes per acre
Density in context46th percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units110Total inventory registered with K-RERA.
Official carpet area6,444 sqmTotal carpet area reported for the project.
Official built-up area14,282 sqmUseful scale context when comparing density and project cost.
Registered land area6,070 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.749Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)121Separate filed counts; these categories may overlap and are not added together.
Covered-parking field121Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberCC/92/2020-21Use this to match the sanctioned drawing set shown by the builder.
Plan approval date08-05-2021
Project start date01-04-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK110100%59 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Single Entry Single Tower411012115 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 110 official flat/unit rows, matching the 110 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK11058.0-59.9 sqm48.8-50.4 sqm110

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Single Entry Single Tower11058.0-59.9 sqm48.8-50.4 sqm110
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001Single Entry Single Tower03 BHK59.5 sqm50.1 sqm1
002Single Entry Single Tower03 BHK58.6 sqm49.3 sqm1
003Single Entry Single Tower03 BHK59.9 sqm50.4 sqm1
004Single Entry Single Tower03 BHK58.1 sqm48.9 sqm1
005Single Entry Single Tower03 BHK58.0 sqm48.8 sqm1
006Single Entry Single Tower03 BHK58.3 sqm49.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

5 of 28 compliance document slots are filed as Not Applicable; the remaining 23 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2025 — which has passed with no OC on file.

See the filed approval statuses and linked documents →

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
SOVAN KUMAR SENAPATI vs Definer VenturesI respectfully request the Hon’ble Authority to: Direct the builder to complete the registration of the apartment immediately without any further delay and hand over the apartment as fully completedAUTHORITY03/07/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (6 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200705/0004581
05-07-2020
Various lapses at Buiders end to RERA and sale agreementDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY
CMP/200728/0006270
28-07-2020
Incomplete Project and Maintenance amountDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/200813/0006352
13-08-2020
Builders wrongful, illegal and forceful approach to extort money before OC on various accountsDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/201123/0007117
23-11-2020
Maintainence burden on residentsDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/201124/0007123
24-11-2020
PMAY GST relaxation refund issue and othersDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/201125/0007122
25-11-2020
Quality of house, maintenance collection. late bescom connection and owners entryDeFINER Hi Life (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

2 of 2 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved25-01-2021Water NOC.pdf
KPTCL- BESCOMApproved31-12-2020Bescom NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRitesh Mehta2141641972Bengaluru Urban, Karnataka - 560070
EngineerAmbrish GBCC/BL -3.6/SE -266/2017-182017Bengaluru Urban, Karnataka - 560032
ArchitectR. SurendranCA/2004/342532005Bengaluru Urban, Karnataka - 560032
ContractorDefiner Ventures-2009Bengaluru Urban, Karnataka - 560080

Builder track record

RERA filing

Definer Ventures has 2 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.35 Cr collected from buyers, ₹0.25 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered78/110 (71%)
Buyer collections in available QPRs₹0.35 Cr
Escrow withdrawals in available QPRs₹0.25 Cr (0.70x collections)
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹0 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹13.3 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Axis Bank Malleshwaram IFSC Code : UTIB0000227 Pin Code : 560003. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub12 km
Kempegowda Int'l Airport14 km
Outer Ring Road / Manyata14 km
Bellandur–Marathahalli belt17 km
MG Road / city centre19 km
Electronic City28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Definer Ventures.
Definer Ventures has 3 projects registered in Bangalore, 1 completed.
7 complaints on the K-RERA register against Definer Ventures in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Krishnarajapuram

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.