Pashmina Brookwoods

Hosakote · Shashwati Realty

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2021declared completionK-RERA registration · read 21 Sep 2026
1,879registered unitsK-RERA registration · read 21 Sep 2026

The record · free to read

Registration read 21 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 21 Sep 2026

Inventory & scale

What this registration contains.

Studio, 1 BHK, 2 BHK
1,895

Filed categories, unchanged · K-RERA registration · read 21 Sep 2026

The whole registration

10.2registered acres

184.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/171015/000556

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2021
Land area41,278 sq m (10.2 acres)
Homes registered1,879
Tower/wing entries5
Unit mix1895 × Studio, 1 BHK, 2 BHK

In context

Density184.2 homes per acre
Density in context98th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units1,879Total inventory registered with K-RERA.
Official carpet area60,741 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area41,278 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)1,777Separate filed counts; these categories may overlap and are not added together.
Open-parking field309Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date05-09-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Studio, 1 BHK, 2 BHK1,895100%60,741 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block -114178178-
Block-214565491-
Block-314394366-
Block-410286286-
Block-510456456-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,865 official flat/unit rows vs 1,879 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
1 BHK1,326275.8-350.6 sqft138.3-180.3 sqft1,326
1BHK221329.2-686.1 sqft169.7-278.9 sqft221
2 BHK199328.4-460.8 sqft169.9-231.4 sqft197 (2 with 0)
STUDIO102202.0-448.9 sqft97.0-224.6 sqft1 (101 with 0)
CH70.0-348.9 sqft0.0-177.9 sqft0 (7 with 0)
2BHK6431.3-442.0 sqft218.3-223.8 sqft6
LOBBY40.0 sqft0.0 sqft0 (4 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block-2565202.0-458.5 sqft97.0-226.1 sqft489 (76 with 0)
Block-5456275.8-441.0 sqft138.3-222.0 sqft456
Block-33810.0-460.8 sqft0.0-226.9 sqft343 (38 with 0)
Block-4285329.4-686.1 sqft170.4-278.9 sqft285
Block -1178327.6-460.2 sqft169.7-231.4 sqft178
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B1A0001Block -102 BHK460.2 sqft230.9 sqft1
B1A0003Block -101 BHK328.9 sqft169.7 sqft1
B1A0004Block -101 BHK327.6 sqft169.7 sqft1
B1A0005Block -102 BHK446.4 sqft216.3 sqft1
B1B0001Block -101 BHK348.9 sqft177.7 sqft1
B1B0002Block -101 BHK330.1 sqft170.9 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 22 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2021, extended (Covid Extension) to 30 Jun 2022 — both dates have passed with no OC on file. An extension application filed on 30 Jun 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (68 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
MADHU SAI KUMAR PAYYAVULA vs SHASHWATI REALTY PVT LTD.1.Project completion as per the agreement, 2. Help me in exit, provided with compensation as i lost trust in the builder, 3. Builder should adhere to pay the Delay compensationAUTHORITY30/06/2023
MR.RAJIV KUMAR KUSHWHA AND ANOTHER vs M/S.SHASHWATI REALTY PVT LTDBuilder must return Pre-emi which is paid by me to Bank from Jul-20 to till date and builder pay further Pre-Emi untill flat is handedover to me (As per agreement)AUTHORITY28/06/2024
Winston Almeida and Irene Almeida vs Shashwati Realty Pvt LtdExit and Full Refund with interest, Legal Costs and such other relief as the Hon'ble court may deem fit to meet the ends of justice.AUTHORITY26/05/2023
MADHAVI VISWANATH vs Shashwati Realty Pvt LtdExit and refund of paid amount with interest compensation as per Section 18 RERAAUTHORITY26/05/2023
Abinash Dash vs Shashwati Realty Pvt LtdInstruct builder to "refund PreEMI amount paid till date and booking amount, cancellation of booking and free exit from project, delay compensation, pay loan amount taken on my name back to IIFL bank"AUTHORITY26/05/2023
Sumanta Sarkar vs Shashwati Realty Pvt LtdWould like to come out of the project and looking for full refund with interest from builder, since builder is unable to deliver the project as per agreement and builder has stopped payment of PRE-EMIAUTHORITY26/05/2023
Dionne D Souza vs Shashwati Realty Pvt Ltd(a) To direct the Respondent to refund the principal amount of Rs. 17,25,578 with an interest of 12 percent interest. Additionally another Rs.3,61,725/- compensation is required as breach in agreemeAUTHORITY26/05/2023
P K RAJESH vs Shashwati Realty Pvt LtdKindly intervene and get the builder to foreclose the loan serviced by PNB Housing Finace and refund the amount due to meAUTHORITY26/05/2023
RAJESH PADINHARE KALATHIL vs Shashwati Realty Pvt LtdKindly intervene and get the builder to foreclose the loan serviced by PNB Housing Finace and refund the amount due to meAUTHORITY26/05/2023
Manjiri Moktali vs Shashwati Realty Pvt LtdI request RERA to ask the respondents to immediately refund the amount of Rs. Rs. 19,72,143 against flat (unit number B4J0005) as proposed by them by transfer to my bank account or by Demand DraftAUTHORITY26/05/2023
Manjiri Moktali vs Shashwati Realty Pvt LtdI request RERA to ask the respondents to immediately refund the amount of Rs. 5,67,200 against flat (unit number B4J0006) as proposed by them, by transfer to my bank account or by Demand Draft.AUTHORITY26/05/2023
MS.RAJANI GEORGE vs M/S.HASHWATI REALTY PVT LTDRefund of Pre-EMI amount paid by me from 2020 till date, Compensation for the delayed possession with appropriate Interest, Direct the builder to expedite the construction process ,Builder to pay EMIAUTHORITY25/04/2024
Blumy A vs SHASHWATI REALTY PRIVATE LIMITEDRefund EMI / Pre - EMI amount paid + Cancellation of booking + Refund booking amount + Closure of loan taken in my name + Free exit from project and delay compensation for breaching agreement.AUTHORITY25/01/2024
Plabon Bhattacharya vs M/S.SHASHWATI REALTYRefund of amount paid with interestAUTHORITY24/02/2026
Piyasa Bhattacharya vs M/S.SHASHWATI REALTY PVT LTDRefund of amount paid with interestAUTHORITY24/02/2026
Shyamal Bhattacharya vs m/s.shashwati realtyRefund of amount paid with interestAUTHORITY24/02/2026
Bindu Madhavi Atmakuru vs PASHMINA BROOK WOODSIt is most humbly prayed before Hon’ble RERA for directing the Builder/ promoter/ Respondent to pay interest on the delay period as per the RERA guidelines in the interest of justice and equity.AUTHORITY22/07/2026
Harshavardhana Bhagat vs Shashwati Realty Pvt LtdDirect the Respondent to refund the amount of 23,35,734 (Rupees Twenty Three Lakhs Thirty Five Thousand Seven Hundred and Thirty Four)AUTHORITY22/07/2026
Chaitra Harady Balakrishna Shetty vs Shashwati Realty Pvt Ltd1. Refund of full amount already paid by the petitioner to respondent 2. Award interest at the rate of 18% till the date of payment 3. Award late payment @15% per sq ft with interestAUTHORITY22/07/2026
sudhir jala vs Shashwati Realty Pvt. Ltd.,It is, therefore, in view of the facts narrated hereinabove, Complainant prays for the refund of an amount of Rs.45,80,098/- (Rupees Forty- Five Lakh Eighty Thousand Ninety-Eight Only) along with penaAUTHORITY22/02/2024
G. VAIDYANATHAN, MADURIMA AIYAR vs M/S SHASHWATI REALTY PRIVATE LIMITEDThe Complainants seeking relef towards Refund of Rs. 3,19,921 (Rupees Three Lakhs NIneteen Thousand Nine Hundred Twenty One Only) alongwith interest of 18% interest for the all these years the ResponAUTHORITY20/11/2023
HARIPRASAD Y S vs PASHMINA BROOKWOODSCOMEPNSATION FOR DELAY IN CONSTRUCTION AND CLEAR THE OUTSTANDING IN THE LOAN ACCOUNT DUE TO NON PAYMENT OF PRE EMI (INTEREST OF LOAN)AUTHORITY19/12/2023
Ranjeet Kumar Paswan vs M/S.SHASHWATI REALTY PVT LTDInterest on delay periodAUTHORITY19/05/2025
MR.M JEYAKUMAR AND ANOTHER vs M/S.SHASHWATI REALTY PVT LTDI would request the respected RERA to direct the builder to pay us the delay compensation for delayed period.AUTHORITY19/02/2024
MR M.JEYAKUMAR AND ANOTHER vs M/S.SHASHWATI REALTY PVT LTDI would request the respected RERA to direct the builder to pay us the delay compensation for delayed period.AUTHORITY19/02/2024
MR M THANGAMANI vs M/S.SHASHWATI REALTY PVT LTDI would request the respected RERA to direct the builder to pay us the delay compensation for delayed period.AUTHORITY19/02/2024
MR.SREE HARSHA BANDARU vs M/S.SHASHWATI REALTY PVT LTD.I need the allotment cancelled and also get a refund of whatever amount I paid to them and bank, I had gone through financially stress as I too have dependents to take care of.AUTHORITY18/12/2024
anima tripathy vs pashmina brook woodsInterest on delay period and Bank penalty for stopping pre EMIs this was supposed to be paid by builder till possessionAUTHORITY18/07/2024
MR.TUSHAR ANANDA BHAMARE vs M/S.SHASHWATI REALTY PVT LTDRecover the full amount including the interest I have paid as a compensation and possession of the flat I have bookedAUTHORITY18/06/2024
ANISH KUMAR vs SHASHWATI REALTY PVT LTDCompensation for the delay possession with appropriate interest and direct the builder for the quick progress on the construction process to handover the possession as early as possible.AUTHORITY16/03/2024
SANA FATIMA vs SHASHWATI REALTY PVT LTDFull refund and compensationAUTHORITY16/03/2024
TAUFEEQ RAWOOF vs SHASHWATI REALTY PVT LTDFull Refund and compensationAUTHORITY16/03/2024
Abhijna Harsha Atri vs pashmina brook woodsClaim sheet has to be reworked as per the agreement and refund of PRE EMI paid by us by the borrower as per the Email and completion of the remaining work in the flat.AUTHORITY16/01/2026
MR ADITY JEURKAR vs M/S.SHASHWATI REALTY PVT LTDRefund INR 17,90,693 paid from 21 March 2023 to 11 February 2015 along with interest and INR 77,653 paid from 03 April 2023 to 02 May 2023 along with interest at MCLR plus 2%AUTHORITY15/07/2024
Arnab Chanda vs PASHMINA BROOKWOODSRefund of payments made from personal fund as well as bank loan along with EMI expensesAUTHORITY15/05/2025
MR PRIYA RANJAN SINGH vs M/S.SHASHWATI REALTY PVT LTDI want my unit Pashmina Brookwoods B2E0306 delivered when it completes, refund of Rs 5,24,624 along with interest, timely refund of pre-EMI Rs 24,686 every month and assurance to not be harassed.AUTHORITY14/10/2024
MR.BHAWANI SINGH SHEKHAWAT vs M/S.SHASHWATI REALTY PVT LTDRefund of Rs. 20,82,594/- (Rupees Twenty Lakhs Eighty Two Thousand Five Hundred and Ninety Four Only) with interest @18% per annum till the date of realization which was paid in the year 2021.AUTHORITY13/11/2023
BIPIN HALAPPA vs SHASHWATI REALTY PVT. LTD.Complete Refund of Amount paid to builder from me as well as loan amount to be closed by builder.AUTHORITY13/06/2023
Madhup Kumar vs M/S.SHASHWATI REALTY PVT LTD.1) 11 lacs EMI ( paid by me ) for 3 years to be refunded 2) Henceforth all EMI to be paid by builder as promised till possession 3) Handover of project at the earliest 4) No further demand of moneyAUTHORITY13/05/2025
Madhup Kumar vs M/S.SHASHWATI REALTY PVT LTD.1) 5.5 lacs EMI ( paid by me ) for 3 years to be refunded 2) Henceforth all EMI to be paid by builder as promised till possession 3) Handover of project at the earliest 4) No further demand of moneyAUTHORITY13/05/2025
Syed Sarfaraj Ahamad vs M/S.SHASHWATI REALTY PVT LTDInterest on the delay periodAUTHORITY13/02/2026
MS.SRIRANITHA JEURKR vs M/S.SHASHWATI REALTY PVT LTD.Direct refund of INR 17,08,528 paid by the Complainant from 21 March 2013 to 11 February 2015 along with interest and INR 77,653 paid from 03 April 2023 to 02 May 202 along with interestAUTHORITY13/02/2025
Trupti Magdum vs M/S.SHASHWATI REALTY PVT LTDRefund and compensation for wrongful information and lack of response to requestsAUTHORITY12/12/2025
Atanu Das vs M/S.SHASHWATI REALTY PVT LTD.Interest on delay periodAUTHORITY11/07/2025
IVAN DSOUZA vs PASHMINA BROOKWOODSVerify on OC if issued. Jusity and sort out buyer issue. Balance Amount to be adjusted with 5Laksh interest paid b y buyer on behalf of builder. Suggest on Occupancy, waited for 8+ years for flat.AUTHORITY10/07/2024
NILAMDHAB ADBEK vs PASHMINA BROOKWOODSCancellation of Booking and compensation with interest of loan emi and booking amount.AUTHORITY10/07/2024
SUSHANT TRIPATHY vs PASHMINA BROOKWOODSInterest on delay period and Bank penalty for stopping pre EMIs this was supposed to be paid by builder till possessionAUTHORITY10/07/2024
Gyanendra Panda vs PASHMINA BROOKWOODSa. Direct the Respondent to refund the amount of 18,57,294 (Rupees Eighteen Lakhs Fifty Seven Thousand Two Hundred and Ninety Four)AUTHORITY10/06/2026
Udaykiran Suragani vs SHASHWATI REALTY PVT LTDCompensation for the delay position with appropriate interest and give orders to the builder for the quick progress on the construction process to hand over the position as early as possible.AUTHORITY09/09/2023
Praveen R vs Shashwati Realty Pvt LtdDelay compansition and full amount refundAUTHORITY09/09/2023
pathan asadullah khan vs pashmina brookwoodsNeed complete refund and pre EMIs cleared.AUTHORITY09/07/2024
Gyanendra Panda vs PASHMINA BROOKWOODSDirect the Respondent to refund the amount of 18,57,294 (Rupees Eighteen Lakhs Fifty Seven Thousand Two Hundred and Ninety Four)AUTHORITY09/06/2026
PRASHANTH KUMAR G vs PASHMINA BROOKWOODSHandover of possession at agreed price and interest on delay period.AUTHORITY08/01/2024
Sudhir Menon vs SUDHIR MENONa. Direct the Respondent to refund the amount of 18,57,443 (Rupees Eighteen Lakhs Fifty Seven Thousand Four Hundred and Forty Three)AUTHORITY07/08/2026
Sudhir Menon vs pashmina brookwoodsa. Direct the Respondent to refund the amount of INR 18,98,010 (Rupees Eighteen Lakhs Ninety Eight Thousand and Ten)AUTHORITY07/08/2026
Nilkantha Chakraborty vs Shashwati Realty Pvt LtdNeed full refund of deposit amount, pashmina should release loan amount bared by me so that my loan is closed with bank without affecting CIBIL and compensation penalty till now as per the market rateAUTHORITY07/04/2025
Rajkumar badtya vs Shashwati Realty Pvt LtdRs 158000 I have paid Since long Time - need refundAUTHORITY07/04/2025
Prashant Ranjan Sinha vs Shashwati Realty Pvt LtdI need complete refund with compensationAUTHORITY07/04/2025
Swati Barman vs SHASHWATI REALTY PVT LTDRefund along with Interest for delay in completion.AUTHORITY03/08/2026
Agnel CJ Kurian vs Shashwati Realty Pvt Ltda. Direct the Respondent to refund the amount of INR 19,29,394 (Rupees Nineteen Lakhs Twenty Nine Thousand Three Hundred and Ninety Four) with interestAUTHORITY03/08/2026
SOUMEN GHOSHAL vs SHASHWATI REALTY PVT.LTD.Need full refund of money - 8,50,000 INR. Cannot effort to pay rent and EMI together. Builder assured that no EMI will be charged to customer till possession but now bank charging EMI from me.AUTHORITY03/08/2023
VINAY SANIL vs SHASWATI REALTY PVT.LTD.Builder to continue paying pre-EMI to IIFL till project completion, builder to provide me with an update on project completion and if there is a lot of uncertainty then i would prefer to exitAUTHORITY03/07/2023
dipti ranjan pradhan vs Shashwati Realty Pvt LtdAllow me for registation and pocession for my flat by taking the actual last installment amount from me after deducting the pendding PreEMI from last installment mentioned in cost sheetAUTHORITY03/06/2026
Chaitanya A Gajjar vs Shashwati Realty Private LimitedWe want the paid money refund and also the pre emi paid till date with compensation of rentals.AUTHORITY02/07/2026
Phani Kumar somayajulu vs PASHIMINA BROOKWOODSNeed Pre EMI reimbursement (From Mar'2020 to Aug'2020), Builder must pay Pre-Emi to bank as agreed until my position, 3. Delay compensationAUTHORITY02/06/2023
UMA DEVI vs PASHMINA BROOKDWOODSCompensation for the delay position and PreEMI reimbursement with appropriate interest; direct the builder to expedite construction process and not to compromise on quality to hand over the positionAUTHORITY02/06/2023
Mohammad Equebal Hussain vs Pashmina Brookwoodspre-EMI reimbursement from April 2020 till date + continued pre-EMI from builder to PNB until procession + delay compensationAUTHORITY02/06/2023
MANOJ KUMAR SAHU vs Pashmina BrookwoodsCompensation for the delay position with appropriate Interest and direct the builder for quick construction process to hand over the position as early as possible with good quality.AUTHORITY02/06/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (29 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190830/0004075
30-08-2019
SUBMISSION OF COMPLAINT UNDER RERA ACT 2016 BY ALLOTTEES OF PASHMINA BROOKWOODS PROJECT AGAINST ITS PROMOTERS/BUILDERSPashmina BrookwoodsDISPOSED AO
CMP/190831/0004092
31-08-2019
Pashmina Brookwoods- Possession delayed and no line of sight for delivery of the unitPashmina BrookwoodsDISPOSED AO
CMP/190929/0004339
29-09-2019
COMPLAINT UNDER THE RERA ACT 2016 BY THE ALLOTTEES OF THE PROJECT "PASHMINA BROOKWOODS" AGAINST ITS BUILDER/DEVELOPERS M/S SHASHWATI REALTY PVT LTD & PASHMINA BUILDERS & DEVELOPERS PVT LTDPashmina BrookwoodsDISPOSED AO
CMP/200816/0006374
16-08-2020
COMPLAINT UNDER SECTION 31 R/W SECTION 71 OF THE REAL ESTATE (REGULATION & DEVELOPMENT) ACT, 2016Pashmina BrookwoodsDISPOSED AUTHORITY FULLBENCH
CMP/200907/0006526
07-09-2020
Construction on hold since October, 2019. Need full refund of money.Pashmina BrookwoodsDISPOSED AUTHORITY FULLBENCH
CMP/200917/0006610
17-09-2020
Compensation for the delay position with appropriate interest and give orders to the builder for the quick progress on the construction process to hand over the position as early as possible.Pashmina BrookwoodsDISPOSED AUTHORITY FULLBENCH
CMP/200924/0006653
24-09-2020
1.Pre Emi reimbursement(from March 2020 to till date to me) 2.Promoter must pay pre EMI to ICICI bank as agreed, 3.Delay compensation to me, 4.pashmina need to expedite the construction processPashmina BrookwoodsDISPOSED AUTHORITY FULLBENCH
CMP/200926/0006671
26-09-2020
Compensation for the delay position and PreEMI reimbursement with appropriate interest; direct the builder to expedite construction process and not to compromise on quality to hand over the positionPashmina BrookwoodsDISPOSED AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectN Sasi Kumar-2000No 19/1 2 nd floor, Vittal Mallaya road
ContractorSimplex Infrastructures Limited-1924S.C.Road, Anand Rao Circle
Structural engineerB E Pruthviraj---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹21.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Fort branch (IFSC HDFC0000060, a/c …9819). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Outer Ring Road / Manyata12 km
Whitefield IT hub12 km
Kempegowda Int'l Airport14 km
Bellandur–Marathahalli belt16 km
MG Road / city centre17 km
Electronic City27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shashwati Realty.
81 complaints on the K-RERA register against Shashwati Realty in Bangalore.

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.