The Magic Faraway Tree Phase 2a

Bengaluru South · Total Environment Building Systems

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
84%construction reportedQ1 2026 filing
7units not bookedof 120 · Q1 2026 filing
31 Dec 2024declared completionK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 25 Oct 2026

Registered units and project size

C20g2
4

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.8registered acres

153.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for The Magic Faraway Tree Phase 2a

K-RERA · PRM/KA/RERA/1251/310/PR/181204/002194

Project facts and comparisons

On the register

Declared completion31 December 2024
Land area3,155 sq m (0.8 acres)
Homes registered120
Tower/wing entries1
Unit mix4 × C20g2

In context

Density153.9 homes per acre
Density in context96th percentile of 791 Bengaluru South projects (median 77.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units120Total inventory registered with K-RERA.
Official carpet area156 sqmTotal carpet area reported for the project.
Registered land area3,155 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)240Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
C20g24100%156 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 02 (B1-as per sanction)29120240-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 120 official flat/unit rows, matching the 120 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK120153.0-156.0 sqm0.0 sqm240

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 02 (B1-as per sanction)120153.0-156.0 sqm0.0 sqm240
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
2021Tower 02 (B1-as per sanction)03BHK156.0 sqm0.0 sqm2
2022Tower 02 (B1-as per sanction)03BHK156.0 sqm0.0 sqm2
2023Tower 02 (B1-as per sanction)03BHK156.0 sqm0.0 sqm2
2024Tower 02 (B1-as per sanction)03BHK156.0 sqm0.0 sqm2
2031Tower 02 (B1-as per sanction)13BHK154.0 sqm0.0 sqm2
2032Tower 02 (B1-as per sanction)13BHK154.0 sqm0.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • Civil — III Additional Senior Civil Judge, Bangalore Rural (2014)

All 24 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2024, extended (Section 6 Extension) to 30 Sep 2026 — both dates have passed with no OC on file. The extension on file was granted on 29 Aug 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/250829/002194) — it has been used, its deadline has also passed, and no further extension is recorded.

See the filed approval statuses and linked documents →

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190408/0002553
08-04-2019
Delay and Breah of AgreementAfter the Rain- Phase 1 (another project by this promoter)DISPOSED AO
CMP/210423/0007919
23-04-2021
Promoter blocking execution and registration of agreement for saleThe Magic Faraway Tree Phase 2 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/211111/0008539
11-11-2021
Refund of the booking amountThe Magic Faraway Tree Phase 2 (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile

Builder track record

RERA filing

Total Environment has 22 other K-RERA-registered projects in our records (average reported construction progress 61%). 9 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹2.26 Cr collected from buyers, ₹2.26 Cr withdrawn from the project's escrow account.

Construction progress98% → 84% (-14 pts)
Units sold/booked as registered113/120 (94%)
Buyer collections in available QPRs₹3.80 Cr
Escrow withdrawals in available QPRs₹3.80 Cr (1.00x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹97.7 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: RATNAKAR BANK Residency Road (IFSC RATN0000156, a/c …9475). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 14 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City14 km
MG Road / city centre15 km
Bellandur–Marathahalli belt19 km
Outer Ring Road / Manyata23 km
Whitefield IT hub27 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Total Environment. View Total Environment's full track record →
Total Environment has 23 projects registered in Bangalore, 4 completed, 3 past RERA deadline.
2 complaints on the K-RERA register against Total Environment in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.63/5

56 reviews for Total Environment in Bangalore
Read 56 reviews on MouthShut →

Other projects by this builder in Bangalore

In That Quiet Earth Phase-2a
Past deadline · 84% built · 100% sold
Pursuit OF A Radical Rhapsody Phase 2
Past deadline · 55% built · 92% sold
Pursuitofaradicalrhapsodyphase1
Past deadline · 88% built · 98% sold
After THE Rain Commercial
Filing overdue · 73% built · 100% sold
After THE Rain-Phase IIB
Filing overdue · 98% built · 97% sold
After THE Rain-Phase IIC
Filing overdue · 68% built · 92% sold

Other RERA-registered projects in Talaghattapura

Major developers building in Talaghattapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.